 Proses Perbaikan Turap Ambrol di Ancol Capai 60 Persen

Landslide Repair in Pademangan Accelerated

Jakarta Water Resouces Dept. continues to speed up work on landslide repairs in Ciliwung River, RT 01/RW 08, Ancol Urban Village, Pademangan, North Jakarta.

Every day we're deploying 40 officers. It's targeted to be completed by the end of December

Until now, part of which is fixed up to 77 meters, or about 60.6 percent of the total length of 127 meters that were damaged.

Governor Monitors Landslide Location in Kalisari

Jakarta Water Resources Dept.'s River and Coast Flow Systems Section, Robert Rajagukguk stated that his side divided the work into two segments. The first stage of the construction up to 77 meter long is now completed already.

"Currently the second phase of the repair is up to 50 meters length," he expressed, Wednesday (11/28).

He added that the Ciliwung River has five meters height. The work itself has been ongoing since October 21, 2018.

"Every day we're deploying 40 officers. It's targeted to be completed by the end of December," he stated.

Linked News
Popular News indeks
  1. Suckermouth Catfish Control for Environmental Preservation

    access_time18-04-2026 remove_red_eye786 personFakhrizal Fakhri
  2. Suckerfish Handling in South Jakarta is Run in Accordance with MUI Recommendations

    access_time21-04-2026 remove_red_eye623 personTiyo Surya Sakti
  3. Jakarta to Hold Citywide Lights-Out Initiative

    access_time24-04-2026 remove_red_eye519 personAldi Geri Lumban Tobing
  4. Jakarta Newcomers Mostly in Productive Age

    access_time22-04-2026 remove_red_eye384 personAldi Geri Lumban Tobing
  5. East Jakarta Steps Up Services to Simplify Population Registration

    access_time20-04-2026 remove_red_eye358 personNurito