Normalisasi Saluran PHB Laut Banda Rampung

Normalization on Laut Banda PHB Channel Completed

Normalization on Jalan Laut Banda's connecting (PHB) channel and East Flood Canal's channel in Duren Sawit, East Jakarta are now completed. It is hoped they could prevent inundation in the area.

From total 652 meters, the open part is 310 meters long and the covered part is 342 meters

East Jakarta SDA Sub-dept. Head, Mustajab mentioned, PHB channel is normalized along 622 meters while East Flood Canal's channel is along 30 meters.

"Laut Banda PHB Channel and KBT crossing channel are integrated. Because water from PHB channel flows to KBT through this crossing channel. Normalization is completed and we just need to clean the remaining debris," he said, Wednesday (12/19).

Water Channel on Jalan Asem Pasar Minggu Normalized

According to him, those channels have the same dimension of width and depth around three meters. Its construction uses U-ditch concrete, but in front of Duren Sawit RSUK it uses box concrete because on the top of it will be planted with crops.

"From total 652 meters, the open part is 310 meters long and the covered part is 342 meters. The open part is located in open area and it can make it easier to do PHB maintenance," he conveyed.

Linked News
Popular News indeks
  1. 129 Motorcycle Parked Illegally in Daan Mogot Controlled

    access_time08-11-2026 remove_red_eye666 personBudhi Firmansyah Surapati
  2. Kampung Melayu Sports Facility Inaugurated to Tackle Brawls

    access_time06-11-2026 remove_red_eye616 personDessy Suciati
  3. Jakarta to Develop Its First Mangrove Botanical Garden

    access_time06-11-2026 remove_red_eye616 personDessy Suciati
  4. Aid for Fire Survivors at Pinus Elok Flats Has Been Distributed

    access_time06-11-2026 remove_red_eye593 personNurito
  5. Kampung Rambutan 1 Reservoir to Combine Flood Control with Public Recreation

    access_time06-11-2026 remove_red_eye581 personAldi Geri Lumban Tobing