You don't have javascript enabled. Good luck with that.
Pencarian
Lalu Lintas (MRLL) di Istora.haknya akan melakukn pembongkaran JPO Karet pada 15 Agustus 2014 dan se
Untuk itu PT MRT akan melakukan Manajemen Rekayasa .
photo istimewa - Beritajakarta.id

MRT Project, Traffic in Istora and Karet Engineered

The PT Mass Rapid Transit is about to impose the Traffic Engineering Management (MRLL) in Istora Sports Hall and Karet areas. It aims to smoothen the construction of the Mass Rapid Transit (MRT)'s underground station at Istora Sports Hall and Bendungan Hilir that has been ongoing since Tuesday (8/12) night.

During demolishment, we plan to impose contra-flow system on the west side of road for lane towards the south (area in front of Sampoerna Strategic Square). It is planned to be carried out on Monday (8/18) night, at 11 PM-4 AM

Director of PT MRT Jakarta, M Nasyir stated to optimize the construction, his party will demolish the Karet's pedestrian bridge on August 15 and is targeted to be done on August 20. 

"During demolishment, we plan to impose one-way traffic system on the west side of road for lane towards the south (area in front of Sampoerna Strategic Square). It is planned to be carried out on Monday (8/18) night, at 11 PM-4 AM," he told, in a press release received by beritajakarta.com, Tuesday (8/12).

One-way Traffic System on Antasari JLNT will Be Permanent

"As compensation, the people can use the pedestrian bridge in front of Le Meridien Hotel," he continued.

Another one-way traffic system would also be imposed on the east of road during the bridge's girder demolishment on the west side . It is scheduled to be conducted on Tuesday (8/19) night at 11 PM-4 AM.

"While for traffic diversion, we cooperate with Jakarta Transportation Department and City Police Traffic Unit. We also installed several traffic lights and banners to facilitate road users," he uttered.

Nasyir disclosed project in Bendungan Hilir will be initiated with work area preparatory consists of median stripping, road markings repainting, temporary roads imposition on the side of the sidewalk and fence installation on median road. It has been carried out since August 12 and is planned to be done on August 20.

"We also do similar project in Senayan and Setiabudi areas as work area preparatory as wide as 30 meters on median road," he told.

He continued, the same with large-scale construction of the MRT's underground station at Istora Sport Hall, also initiated with work area preparatory in the media center that began on Tuesday (8/12) until (8/25) night. As for the work area required at Istora is 28 meters wide, thus traffic engineering needed.

"As the initial stage, the first stage is about Guide Wall construction, and then proceed with Diaphragm Wall (D-Wall), excavation as well as construction of the main structure of the station that was scheduled to be completed on April 30, 2016," he concluded.

Linked News
Popular News indeks
  1. MSMEs Bazaar Held at Binus Anggrek Campus

    access_time30-10-2024 remove_red_eye966 personTP Moan Simanjuntak
  2. 250 High School Students in N. Jakarta Learn to Create Digital Content

    access_time01-11-2024 remove_red_eye779 personBudhi Firmansyah Surapati
  3. 18 School Principals Participate in Public Agency E-Monev Presentation

    access_time02-11-2024 remove_red_eye445 personFolmer
  4. South Jakarta City Government Accelerates Stop BABS

    access_time31-10-2024 remove_red_eye410 personTiyo Surya Sakti
  5. Tanah Tinggi Residents Participate in Computer Operator Training

    access_time02-11-2024 remove_red_eye351 personBudhi Firmansyah Surapati