Channel on Jalan Kartini Raya Normalized

Some 75 personnel under Central Jakarta Water Resources Sub-agency is normalizing a 900-meter long water channel on Jalan Kartini Raya, Sawah Besar 

The work progress has touched 60 percent

"The work progress has touched 60 percent," expressed Sawah Besar Sub-district Water Resources Executing Unit Head, Nanang Kusnandi, Wednesday (8/7).

Channel on Jalan Kalibata Utara II Normalized

The channel will be widened from 60 to 80 cm. To optimize it, heavy equipment has been sent to the location.

"It is targeted to be completed in the upcoming September," he stated.

Linked News
Popular News indeks
  1. Jakarta Taps MSMEs and Creative Economy to Secure Global Top 50 Spot

    access_time11-07-2026 remove_red_eye1578 personAldi Geri Lumban Tobing
  2. Ciliwung River Normalization Accelerated, Pramono Ensures Land Acquisition Without Intermediaries

    access_time10-07-2026 remove_red_eye1437 personDessy Suciati
  3. Blocked Drain on Jalan Palmerah Utara is Being Repaired

    access_time10-07-2026 remove_red_eye1301 personFolmer
  4. Jalan Kebon Kelapa I Repaved

    access_time07-07-2026 remove_red_eye1094 personNurito
  5. Pramono Inaugurates Mayapada Hospital to Improve Healthcare Services

    access_time09-07-2026 remove_red_eye965 personDessy Suciati