Kepu Selatan Channel Dredging Targeted to Be Complete in October

The Kepu Selatan Connecting Channel dredging process on Jalan Kepu Selatan, Kemayoran Urban Village, Kemayoran Sub-district, Central Jakarta has reached 90 percent.

It is targeted to be finished in two weeks ahead

"It is targeted to be finished in two weeks ahead," expressed Kemayoran Sub-district Water Resources Executing Unit Head, Yursid Suryanegara, Wednesday (9/18).

This channel is targeted to be dredged up to 329 meters length that has been ongoing since August. Thus far it has reached 269 meters. 

Pluit Reservoir Dredging Has Reached 30 Percent

"We dredge mud and waste that triggers siltation up to 50 centimeters. We normalize the channel up to 120 centimeters depth," he explained.

From the channel, the personnel have transported 135 cubic meters of mud and waste.

"To do it, we have sent seven personnel to the location," he told.

Linked News
Popular News indeks
  1. Jakarta Government Guarantees Full Medical Care for Bantargebang Landslide Victims

    access_time09-03-2026 remove_red_eye1296 personDessy Suciati
  2. Commission E Supports Restricting Children's Access to Social Media

    access_time09-03-2026 remove_red_eye1126 personFakhrizal Fakhri
  3. Affordable and High-Quality Staple Goods Offered at Ramadan Bazaar

    access_time09-03-2026 remove_red_eye838 personAldi Geri Lumban Tobing
  4. Jakarta Planetarium Rolls Out Varied Shows for Eid al-Fitr Holiday

    access_time11-03-2026 remove_red_eye290 personAldi Geri Lumban Tobing
  5. Jakarta Speeds Up Flood Mitigation Efforts

    access_time08-03-2026 remove_red_eye288 personAldi Geri Lumban Tobing