 Pengurasan PHB Kepu Selatan Mencapai 90 Persen.

Kepu Selatan Channel Dredging Targeted to Be Complete in October

The Kepu Selatan Connecting Channel dredging process on Jalan Kepu Selatan, Kemayoran Urban Village, Kemayoran Sub-district, Central Jakarta has reached 90 percent.

It is targeted to be finished in two weeks ahead

"It is targeted to be finished in two weeks ahead," expressed Kemayoran Sub-district Water Resources Executing Unit Head, Yursid Suryanegara, Wednesday (9/18).

This channel is targeted to be dredged up to 329 meters length that has been ongoing since August. Thus far it has reached 269 meters. 

Pluit Reservoir Dredging Has Reached 30 Percent

"We dredge mud and waste that triggers siltation up to 50 centimeters. We normalize the channel up to 120 centimeters depth," he explained.

From the channel, the personnel have transported 135 cubic meters of mud and waste.

"To do it, we have sent seven personnel to the location," he told.

Linked News
Popular News indeks
  1. Commission E Enlists Religious Leaders to Fight Drugs and Violence

    access_time24-07-2026 remove_red_eye1226 personFakhrizal Fakhri
  2. Jakarta Supports Social Media Restrictions for Children

    access_time20-07-2026 remove_red_eye1203 personFakhrizal Fakhri
  3. The 2026 SEA V Cup Officially Begins

    access_time23-07-2026 remove_red_eye1077 personAldi Geri Lumban Tobing
  4. Fire at Spark Sport Academy Pondok Bambu Successfully Extinguished

    access_time20-07-2026 remove_red_eye1016 personNurito
  5. Jakarta Government Prepares Rp 249 B to Renovate Four Schools

    access_time25-07-2026 remove_red_eye790 personDessy Suciati