October, Mud Dredging in Cengkareng BCT River Finished

The Central Jakarta Water Resources Sub-agency reported that the mud dredging process in the BCT River, Cengkareng has touched 50 percent.

It is targeted to be finish by the end of October

"It is targeted to be finish by the end of October," expressed Raw, Clean and Waste Waters Flood Handling Maintenance Section Head, Imam Prasetyo, Thursday (9/25).

It is carried out up to 1,799 meters length with 1.5 meters depth. To do it, two heavy equipments type long-arm and amphibian excavators have been sent to the location.

Mud Dredging in Maja River Has Touched 50 Percent

"We also have sent dump truck plus 15 personnel. This dredging is part of the effort to overcome the puddles around Taman Palem," he stated.

Linked News
Popular News indeks
  1. Pramono Affirms Commitment to Enhancing Regional Financial Management Quality

    access_time02-04-2026 remove_red_eye794 personTiyo Surya Sakti
  2. Pramono Calls for Enhanced Synergy at DPRD Post-Eid Gathering

    access_time30-03-2026 remove_red_eye704 personDessy Suciati
  3. Banners Prohibiting Illegal Parking Levies Installed at Blok M Square

    access_time02-04-2026 remove_red_eye640 personTiyo Surya Sakti
  4. Kampung Rambutan Terminal Sees Increase in Intercity Bus Passengers

    access_time03-04-2026 remove_red_eye598 personNurito
  5. Gov Pramono: Jakarta Prepared to Adopt Weekly WFH Scheme

    access_time30-03-2026 remove_red_eye448 personDessy Suciati