Normalisasi Saluran Air di Jl Kayu Manis IX Capai 95 Persen

Process of Channel Normalization on Jl. Kayu Manis IX Reaches 95 Percent

Water channel normalization conducted on Jalan Kayu Manis IX, RT 04/08, Matraman, East Jakarta has reached 95 percent.

This normalization is targeted to complete on December 19

East Jakarta SDA Sub-department's Development Section Head, Tengku Saugi Zikri explained, his side has started to normalize that 724-meter channel since mid of October 2019.

"This normalization is targeted to complete on December 19," he stated, Sunday (12/15).

Rp 2.01 Billion Spent to Normalize Channel on Jalan Kemuning Raya

According to him, currently his side is installing U-ditch concrete with size 60x60 centimeters on the channel.

"We construct channel on Jalan Kayu Manis IX to connect with Kayumanis Timur connecting (PHB) channel," he informed.

Linked News
Popular News indeks
  1. Cilandak Drainage Upgraded to Mitigate Flooding

    access_time27-01-2026 remove_red_eye870 personTiyo Surya Sakti
  2. South Jakarta Tackles 38 Dengue Cases to Prevent Outbreak

    access_time02-02-2026 remove_red_eye721 personTiyo Surya Sakti
  3. Pramono: Jakarta Government Acts Swiftly to Tackle Flooding

    access_time30-01-2026 remove_red_eye370 personDessy Suciati
  4. Several Microtrans Routes Diverted

    access_time31-01-2026 remove_red_eye369 personAldi Geri Lumban Tobing
  5. Jakarta Showers to Make Way for Partly Cloudy Skies

    access_time30-01-2026 remove_red_eye362 personDessy Suciati
close