 Pengerjaan Normalisais Saluran di Jalan Panca Raya Capai 59 Persen

Channel Normalization at Jalan Panca Raya Reaches 59 Percent

Normalization that has been carried out since October 15 is up to 220 meters length

The Kemayoran Sub-district Water Resources Executing Unit, Central Jakarta is normalizing a water channel stood atop Jalan Panca Raya, Serdang Urban Village. Its progress has reached 59 percent.

"Normalization that has been carried out since October 15 is up to 220 meters length," expressed Kemayoran Sub-district Water Resources (SDA) Executing Unit Head, Thursday (12/26).

Process of Channel Normalization on Jl. Kayu Manis IX Reaches 95 Percent

Besides dredging mud and garbage, it is also carried out by installing an U-ditch in the size of 60x60x120 cm.

"We hope it can minimize flooding in the future. We'll finish it soon," he stated.

Linked News
Popular News indeks
  1. Jakarta Council Begins Deliberations on New Population and Housing Bylaws

    access_time21-08-2026 remove_red_eye1830 personFakhrizal Fakhri
  2. Pramono: Independence must Be Manifested Through Concrete Action

    access_time17-08-2026 remove_red_eye686 personDessy Suciati
  3. Pramono Commends Madurese Community for Their Vital Role in Building Jakarta

    access_time19-08-2026 remove_red_eye658 personDessy Suciati
  4. Pramono Vows to Prioritize Jakarta’s Strategic Development

    access_time22-08-2026 remove_red_eye573 personDessy Suciati
  5. Jakarta Agrees on Rp79.59T Revised 2026 Budget Framework

    access_time21-08-2026 remove_red_eye387 personFakhrizal Fakhri