Channel Normalization at Jalan Panca Raya Reaches 59 Percent

Normalization that has been carried out since October 15 is up to 220 meters length

The Kemayoran Sub-district Water Resources Executing Unit, Central Jakarta is normalizing a water channel stood atop Jalan Panca Raya, Serdang Urban Village. Its progress has reached 59 percent.

"Normalization that has been carried out since October 15 is up to 220 meters length," expressed Kemayoran Sub-district Water Resources (SDA) Executing Unit Head, Thursday (12/26).

Process of Channel Normalization on Jl. Kayu Manis IX Reaches 95 Percent

Besides dredging mud and garbage, it is also carried out by installing an U-ditch in the size of 60x60x120 cm.

"We hope it can minimize flooding in the future. We'll finish it soon," he stated.

Linked News
Popular News indeks
  1. Transjakarta Targets Planting 100,000 Mangroves

    access_time12-07-2025 remove_red_eye393 personBudhi Firmansyah Surapati
  2. Rano Karno Celebrates City's Anniversary with Kamal Residents

    access_time12-07-2025 remove_red_eye389 personFolmer
  3. Residents Enthusiastically Enjoy the Car Free Day in Kebayoran Lama

    access_time13-07-2025 remove_red_eye344 personTiyo Surya Sakti
  4. Traffic Engineering on Jalan Otista to Begin July 20 Due to JPO Revitalization

    access_time17-07-2025 remove_red_eye318 personAldi Geri Lumban Tobing
  5. MRT Jakarta Considers Route Expansion to South Tangerang

    access_time13-07-2025 remove_red_eye312 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik