 Pengerjaan Tanggul Pulau Lancang Mencapai 50 Persen
.
photo Suparni - Beritajakarta.id

Dike Casting in Lancang Island Targeted to Finish End of May

Thousand Islands Water Resources (SDA) Sub-agency personnel continue dike casting project on the northern side of RT 03/02 Lancang Island, Pari Island Urban Village, South Thousand Islands.

Its process has reached 50 percent

Thousand Islands SDA Sub-Agency Head, Abdul Rauf stated, dike as long as 158 meters will be casted thus later it can be used as inspection road, jogging track, as well as beach abrasion barrier.

"Its process has reached 50 percent," he said, Tuesday (5/5).

Ciliwung PHB Retaining Wall has Been Repaired

For this project, his side deployed 19 PJLP personnel every day.

"Our target is to finish it by the end of this month," he asserted.

Linked News
Popular News indeks
  1. Rano Inspects Location and Delivers Aid to Fire Victims in Bukit Duri

    access_time20-07-2025 remove_red_eye668 personNurito
  2. Assistance Continues to Be Provided to Bukit Duri Fire Victims

    access_time20-07-2025 remove_red_eye454 personNurito
  3. Rano Ensures Swift Action in Bukit Duri Fire Handling

    access_time19-07-2025 remove_red_eye396 personFakhrizal Fakhri
  4. C. Jakarta TP PKK Grows 2,470 Chili and Tomato Seedlings

    access_time18-07-2025 remove_red_eye389 personFolmer
  5. Munjirin Leads Simultaneous Planting at RPTRA Rawa Jaya

    access_time18-07-2025 remove_red_eye384 personNurito

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik