Pengerukan Kali Apuran Cengkareng Barat Sudah 50 Persen

Apuran River Dredging is Targeted to Finish in Mid of July

West Jakarta Government continues to optimize flood prevention program, including to dredge Apuran River that located in Cengkareng Urban Village, Cengkareng. The dredging process has reached 50 percent and is targeted to finish in mid of July 2020.

Now, we have dredged 300 meters or 50 percent of the target

West Jakarta Water Resources (SDA) Sub-agency's Maintenance of Flood Control System for Raw Clean Water and Wastewater Section Head, Wawan stated, his side started dredging Apuran River since June 17. In order to increase capacity and flow of the river, his side planned to dredge it as long as 600 meters.

"Now, we have dredged 300 meters or 50 percent of the target," he informed, Tuesday (6/30).

East Jakarta Optimizes Flood Prevention Programs

His side deployed 14 personnel, 2 heavy equipments such as standard backhoe and amphibious excavator units, as well as 10 dump trucks with capacity 8 square meters and 3 tronton trucks with capacity 13 square meters.

"Until now, we have transported 403 cubic meters of mud. We plan to dredge around 70-100 centimeters," he closed.

Linked News
Popular News indeks
  1. Jakarta Government Guarantees Full Medical Care for Bantargebang Landslide Victims

    access_time09-03-2026 remove_red_eye1287 personDessy Suciati
  2. Commission E Supports Restricting Children's Access to Social Media

    access_time09-03-2026 remove_red_eye1116 personFakhrizal Fakhri
  3. Affordable and High-Quality Staple Goods Offered at Ramadan Bazaar

    access_time09-03-2026 remove_red_eye829 personAldi Geri Lumban Tobing
  4. Don’t Miss Ramadan Jazz Festival 2026 at Cut Meutia Mosque

    access_time07-03-2026 remove_red_eye368 personFolmer
  5. Fighting Online Gambling, Pramono Calls for QR Code Sweep in Public Areas

    access_time07-03-2026 remove_red_eye355 personDessy Suciati