You don't have javascript enabled. Good luck with that.
Pencarian
Pembangunan FO Cakung Capai 71 Persen

Cakung Flyover Development Process Has Reached 71 Percent

The Cakung Flyover development process in East Jakarta has reached 71 percent and now has entered the girder lifting stage.

The work has touched 71 percent from the initial plan was 66 percent

Jakarta Bina Marga Agency Head Hari Nugroho said work plans and realization had a positive deviation of five percent. The girder lifting was mainly on the west side of the East Flood Canal (KBT) and flyover girders that cross the railway tracks.

"The work has touched 71 percent from the initial plan was 66 percent. So there is a positive deviation of five percent," he said, Wednesday (9/9).

Illegal Parking Income in Cakung Flyover Reaches Rp 18 M

He expressed around 84 girders would be installed and currently it had reached 72 girders as of September 7. This flyover was built to parse traffic jam caused by railway crossings and minimize accidents.

"That railway crossings will be closed down. So, drivers will be directed through the Cakung Flyover. It is targeted to be complete by the end of this year," he hoped.

Linked News
Popular News indeks
  1. Cilandak Drainage Upgraded to Mitigate Flooding

    access_time27-01-2026 remove_red_eye868 personTiyo Surya Sakti
  2. TransJabodetabek Expansion, a Strategic Step to Increase Public Transportation Use

    access_time26-01-2026 remove_red_eye424 personFakhrizal Fakhri
  3. Jakarta Prepares OMC and 200 Excavators to Prevent Flood

    access_time26-01-2026 remove_red_eye371 personDessy Suciati
  4. Jakarta Showers to Make Way for Partly Cloudy Skies

    access_time30-01-2026 remove_red_eye358 personDessy Suciati
  5. Several Microtrans Routes Diverted

    access_time31-01-2026 remove_red_eye355 personAldi Geri Lumban Tobing
close