Pembangunan FO Cakung Capai 71 Persen

Cakung Flyover Development Process Has Reached 71 Percent

The Cakung Flyover development process in East Jakarta has reached 71 percent and now has entered the girder lifting stage.

The work has touched 71 percent from the initial plan was 66 percent

Jakarta Bina Marga Agency Head Hari Nugroho said work plans and realization had a positive deviation of five percent. The girder lifting was mainly on the west side of the East Flood Canal (KBT) and flyover girders that cross the railway tracks.

"The work has touched 71 percent from the initial plan was 66 percent. So there is a positive deviation of five percent," he said, Wednesday (9/9).

Illegal Parking Income in Cakung Flyover Reaches Rp 18 M

He expressed around 84 girders would be installed and currently it had reached 72 girders as of September 7. This flyover was built to parse traffic jam caused by railway crossings and minimize accidents.

"That railway crossings will be closed down. So, drivers will be directed through the Cakung Flyover. It is targeted to be complete by the end of this year," he hoped.

Linked News
Popular News indeks
  1. Pram-Rano Attend Bung Karno Festival at Proklamasi Park

    access_time20-06-2026 remove_red_eye1139 personFolmer
  2. 21 Parking Spots to Make Your Jakarta 499th Anniversary Experience Seamless

    access_time26-06-2026 remove_red_eye852 personAldi Geri Lumban Tobing
  3. Celebrating Jakarta`s 499th Anniversary at HI, Please Use Public Transportation

    access_time26-06-2026 remove_red_eye673 personAldi Geri Lumban Tobing
  4. JIS-Ancol Integrated Infrastructure Officially Activated

    access_time23-06-2026 remove_red_eye635 personDessy Suciati
  5. Over 11 Kilometers of Overhead Utility Cables Removed in West Jakarta

    access_time26-06-2026 remove_red_eye618 personBudhi Firmansyah Surapati