Pembangunan FO Cakung Capai 71 Persen

Cakung Flyover Development Process Has Reached 71 Percent

The Cakung Flyover development process in East Jakarta has reached 71 percent and now has entered the girder lifting stage.

The work has touched 71 percent from the initial plan was 66 percent

Jakarta Bina Marga Agency Head Hari Nugroho said work plans and realization had a positive deviation of five percent. The girder lifting was mainly on the west side of the East Flood Canal (KBT) and flyover girders that cross the railway tracks.

"The work has touched 71 percent from the initial plan was 66 percent. So there is a positive deviation of five percent," he said, Wednesday (9/9).

Illegal Parking Income in Cakung Flyover Reaches Rp 18 M

He expressed around 84 girders would be installed and currently it had reached 72 girders as of September 7. This flyover was built to parse traffic jam caused by railway crossings and minimize accidents.

"That railway crossings will be closed down. So, drivers will be directed through the Cakung Flyover. It is targeted to be complete by the end of this year," he hoped.

Linked News
Popular News indeks
  1. Transjakarta Brings Lunar New Year Festivities to Public Transport

    access_time16-02-2026 remove_red_eye971 personAldi Geri Lumban Tobing
  2. Free Transit Card Applications Skyrocket 143%, Passing 76k Mark

    access_time20-02-2026 remove_red_eye932 personAldi Geri Lumban Tobing
  3. Jakarta Govt-City Council Step Up Coordination to Address Key Urban Challenges

    access_time22-02-2026 remove_red_eye825 personFakhrizal Fakhri
  4. Public Works Agency Gets Transjakarta Corridor 13 Back in Tip-Top Shape

    access_time17-02-2026 remove_red_eye709 personAldi Geri Lumban Tobing
  5. Chinese New Year Holiday, Ancol Flocked by Visitors

    access_time16-02-2026 remove_red_eye606 personAnita Karyati