Pembangunan FO Cakung Capai 71 Persen

Cakung Flyover Development Process Has Reached 71 Percent

The Cakung Flyover development process in East Jakarta has reached 71 percent and now has entered the girder lifting stage.

The work has touched 71 percent from the initial plan was 66 percent

Jakarta Bina Marga Agency Head Hari Nugroho said work plans and realization had a positive deviation of five percent. The girder lifting was mainly on the west side of the East Flood Canal (KBT) and flyover girders that cross the railway tracks.

"The work has touched 71 percent from the initial plan was 66 percent. So there is a positive deviation of five percent," he said, Wednesday (9/9).

Illegal Parking Income in Cakung Flyover Reaches Rp 18 M

He expressed around 84 girders would be installed and currently it had reached 72 girders as of September 7. This flyover was built to parse traffic jam caused by railway crossings and minimize accidents.

"That railway crossings will be closed down. So, drivers will be directed through the Cakung Flyover. It is targeted to be complete by the end of this year," he hoped.

Linked News
Popular News indeks
  1. Suckermouth Catfish Control for Environmental Preservation

    access_time18-04-2026 remove_red_eye783 personFakhrizal Fakhri
  2. Jakarta Regional Budget Spending Reaches Rp10.38 Trillion in Q1

    access_time17-04-2026 remove_red_eye713 personDessy Suciati
  3. Suckerfish Handling in South Jakarta is Run in Accordance with MUI Recommendations

    access_time21-04-2026 remove_red_eye622 personTiyo Surya Sakti
  4. Job Absorption Rises in Jakarta

    access_time17-04-2026 remove_red_eye615 personDessy Suciati
  5. Training and Certification Boost Tourism Workforce Competitiveness

    access_time17-04-2026 remove_red_eye596 personAldi Geri Lumban Tobing