Pembangunan FO Cakung Capai 71 Persen
.
photo Aldi Geri Lumban Tobing - Beritajakarta.id

Cakung Flyover Development Process Has Reached 71 Percent

The Cakung Flyover development process in East Jakarta has reached 71 percent and now has entered the girder lifting stage.

The work has touched 71 percent from the initial plan was 66 percent

Jakarta Bina Marga Agency Head Hari Nugroho said work plans and realization had a positive deviation of five percent. The girder lifting was mainly on the west side of the East Flood Canal (KBT) and flyover girders that cross the railway tracks.

"The work has touched 71 percent from the initial plan was 66 percent. So there is a positive deviation of five percent," he said, Wednesday (9/9).

Illegal Parking Income in Cakung Flyover Reaches Rp 18 M

He expressed around 84 girders would be installed and currently it had reached 72 girders as of September 7. This flyover was built to parse traffic jam caused by railway crossings and minimize accidents.

"That railway crossings will be closed down. So, drivers will be directed through the Cakung Flyover. It is targeted to be complete by the end of this year," he hoped.

Linked News
Popular News indeks
  1. Sudirman-Thamrin's Car Free Day Held on June 1, 2025

    access_time29-05-2025 remove_red_eye517 personAldi Geri Lumban Tobing
  2. Rano: Pancasila is the Big House for Indonesia's Diversity

    access_time02-06-2025 remove_red_eye503 personBudhi Firmansyah Surapati
  3. Rano Requests PBSI to Hold Governor's Cup Championship

    access_time31-05-2025 remove_red_eye399 personBudhi Firmansyah Surapati
  4. City Government and Hotels Promote Betawi Culture to the Global Stage

    access_time30-05-2025 remove_red_eye376 personFakhrizal Fakhri
  5. Ragunan Zoo Bustling with Holiday Visitors

    access_time30-05-2025 remove_red_eye364 personTiyo Surya Sakti

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik