Pembangunan FO Cakung Capai 71 Persen
.
photo Aldi Geri Lumban Tobing - Beritajakarta.id

Cakung Flyover Development Process Has Reached 71 Percent

The Cakung Flyover development process in East Jakarta has reached 71 percent and now has entered the girder lifting stage.

The work has touched 71 percent from the initial plan was 66 percent

Jakarta Bina Marga Agency Head Hari Nugroho said work plans and realization had a positive deviation of five percent. The girder lifting was mainly on the west side of the East Flood Canal (KBT) and flyover girders that cross the railway tracks.

"The work has touched 71 percent from the initial plan was 66 percent. So there is a positive deviation of five percent," he said, Wednesday (9/9).

Illegal Parking Income in Cakung Flyover Reaches Rp 18 M

He expressed around 84 girders would be installed and currently it had reached 72 girders as of September 7. This flyover was built to parse traffic jam caused by railway crossings and minimize accidents.

"That railway crossings will be closed down. So, drivers will be directed through the Cakung Flyover. It is targeted to be complete by the end of this year," he hoped.

Linked News
Popular News indeks
  1. Five Transjabodetabek Routes will Be Added to Tackle Traffic Congestion

    access_time09-05-2025 remove_red_eye665 personDessy Suciati
  2. Tanah Abang SDA Taskforce Normalizes Channels in Two Locations

    access_time12-05-2025 remove_red_eye443 personFolmer
  3. Munjirin Optimizes Physical and Non-Physical Development in East Jakarta

    access_time08-05-2025 remove_red_eye377 personNurito
  4. Community Work Held to Clean Environment in Petamburan

    access_time11-05-2025 remove_red_eye346 personFolmer
  5. Baduy Tribe Meets Pramono-Rano, Leaves Message of Protecting Nature

    access_time09-05-2025 remove_red_eye291 personDessy Suciati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik