Underpass Senen Extention Diuji Coba Mulai November 2020

Senen Underpass Extension will Be Tested in November 2020

Progress of extension construction on Senen Underpass now has reached 87 percent. It is faster than the predetermined target plan.

We are optimistic that the construction can finish in December

Jakarta Bina Marga Agency Head, Hari Nugroho conveyed, construction progress reached 87 percent, while the initial plan was 86 percent. It means there was positive deviation about one percent.

Central Jakarta Bina Marga Focuses on Anticipating Inundation on the Roads

This construction is focusing on finishing road work under the tunnel and installing ACP wall as facing wall thus the tunnel walls look beautiful.

After seeing the progress, he was optimistic that Senen Underpass Extension could be tested by the end of November 2020.

"We are optimistic that the construction can finish in December and be inaugurated in the end of December. At the end of November, we will test it for open traffic while fixing what we miss. In mid December, it will be ready for public use," he mentioned.

Moreover, his side is also restoring sidewalk and arranging drainage channels both above underpass and under the tunnel.

Also, other works that are on process such as underpass pump to remove rain water from tunnel, mechanical electrical work, and artistic lighting work both in tunnels, pedestrian bridges (JPO)s, and Transjakarta bus shelters.

"We still have to finish construction on JPOs which equipped with elevator at Pasar Senen JPO and JPO in front of Atrium, and repairing damaged roads due to project work using hot mix layer," he explained.

Linked News
Popular News indeks
  1. Jakarta Endorses New Housing Project for Residents on Railway Embankments

    access_time28-03-2026 remove_red_eye2398 personDessy Suciati
  2. Pramono Affirms Commitment to Enhancing Regional Financial Management Quality

    access_time02-04-2026 remove_red_eye780 personTiyo Surya Sakti
  3. Pramono Calls for Enhanced Synergy at DPRD Post-Eid Gathering

    access_time30-03-2026 remove_red_eye684 personDessy Suciati
  4. Banners Prohibiting Illegal Parking Levies Installed at Blok M Square

    access_time02-04-2026 remove_red_eye626 personTiyo Surya Sakti
  5. Jakarta Environmental Sub-agency Clears Trash Buildup at Kramat Jati Wholesale Market

    access_time28-03-2026 remove_red_eye457 personNurito