Progres Pembangunan JIS Capai 34,13 Persen
.
photo Wuri Setyaningsih - Beritajakarta.id

Process of JIS Construction Reaches 34.13 Percent

PT. Jakarta Propertindo (Jakpro) continues the construction work of Jakarta International Stadium (JIS), in Tanjung Priok, North Jakarta. Entering the 61st week, its progress has reached 34.13 percent.

We are currently installing hybrid grass in training field 1

Corporate Communication and Commercial for JIS Project, Arnold Kindangen mentioned, his side deployed 1,700 workers for JIS construction project.

"We are currently installing hybrid grass in training field 1. Previously, we have completed grass installation in training field 2," he added, Thursday (11/5).

Jakpro is Committed to Finish JIS Project on Time

Grass installation is targeted to finish in December 2020. Next, his side still needs to finish constructing 8 main columns using slipform and start the pierhead work, precast installation on southern side of the stage.

"This project is estimated to employ 5,000 workers in 2021. We hope they can contribute to recover the economic since this project involves many vendors related to construction and material supply," he said.

Linked News
Popular News indeks
  1. Transjakarta Targets Planting 100,000 Mangroves

    access_time12-07-2025 remove_red_eye415 personBudhi Firmansyah Surapati
  2. Rano Karno Celebrates City's Anniversary with Kamal Residents

    access_time12-07-2025 remove_red_eye399 personFolmer
  3. Residents Enthusiastically Enjoy the Car Free Day in Kebayoran Lama

    access_time13-07-2025 remove_red_eye355 personTiyo Surya Sakti
  4. Traffic Engineering on Jalan Otista to Begin July 20 Due to JPO Revitalization

    access_time17-07-2025 remove_red_eye327 personAldi Geri Lumban Tobing
  5. MRT Jakarta Considers Route Expansion to South Tangerang

    access_time13-07-2025 remove_red_eye318 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik