Progres Pembangunan JIS Capai 34,13 Persen

Process of JIS Construction Reaches 34.13 Percent

PT. Jakarta Propertindo (Jakpro) continues the construction work of Jakarta International Stadium (JIS), in Tanjung Priok, North Jakarta. Entering the 61st week, its progress has reached 34.13 percent.

We are currently installing hybrid grass in training field 1

Corporate Communication and Commercial for JIS Project, Arnold Kindangen mentioned, his side deployed 1,700 workers for JIS construction project.

"We are currently installing hybrid grass in training field 1. Previously, we have completed grass installation in training field 2," he added, Thursday (11/5).

Jakpro is Committed to Finish JIS Project on Time

Grass installation is targeted to finish in December 2020. Next, his side still needs to finish constructing 8 main columns using slipform and start the pierhead work, precast installation on southern side of the stage.

"This project is estimated to employ 5,000 workers in 2021. We hope they can contribute to recover the economic since this project involves many vendors related to construction and material supply," he said.

Linked News
Popular News indeks
  1. Jakarta Administration Steps Up Proactive Fire Prevention Efforts

    access_time09-10-2026 remove_red_eye535 personDessy Suciati
  2. New Kelapa Gading-Pulogadung Road to Ease Traffic and Improve Access

    access_time10-10-2026 remove_red_eye524 personAldi Geri Lumban Tobing
  3. MRT Jakarta Integrates Ticket Payments with JakLingko from October 12

    access_time10-10-2026 remove_red_eye523 personAldi Geri Lumban Tobing
  4. Kramat Pulo Fire Survivors Get Help Replacing School Documents

    access_time09-10-2026 remove_red_eye515 personFolmer
  5. Basic Supplies Distributed to Pinang Ranti Fire Survivors

    access_time09-10-2026 remove_red_eye504 personNurito