You don't have javascript enabled. Good luck with that.
Pencarian
Progres Pembangunan JIS Capai 34,13 Persen

Process of JIS Construction Reaches 34.13 Percent

PT. Jakarta Propertindo (Jakpro) continues the construction work of Jakarta International Stadium (JIS), in Tanjung Priok, North Jakarta. Entering the 61st week, its progress has reached 34.13 percent.

We are currently installing hybrid grass in training field 1

Corporate Communication and Commercial for JIS Project, Arnold Kindangen mentioned, his side deployed 1,700 workers for JIS construction project.

"We are currently installing hybrid grass in training field 1. Previously, we have completed grass installation in training field 2," he added, Thursday (11/5).

Jakpro is Committed to Finish JIS Project on Time

Grass installation is targeted to finish in December 2020. Next, his side still needs to finish constructing 8 main columns using slipform and start the pierhead work, precast installation on southern side of the stage.

"This project is estimated to employ 5,000 workers in 2021. We hope they can contribute to recover the economic since this project involves many vendors related to construction and material supply," he said.

Linked News
Popular News indeks
  1. Central Jakarta Helps 879 Residents Retrieve Withheld Diplomas

    access_time30-10-2026 remove_red_eye601 personFolmer
  2. Jakarta to Host World Cities Culture Summit 2027

    access_time31-10-2026 remove_red_eye600 personBudhi Firmansyah Surapati
  3. Tourism Industry Workforce Capacity Continues to Be Improved

    access_time30-10-2026 remove_red_eye587 personAldi Geri Lumban Tobing
  4. Free Health Checks and TB Screening Held at RPTRA Tamplas Bambu

    access_time30-10-2026 remove_red_eye578 personNurito
  5. Road to Larata Run 2026 Combines Running with Public Transport

    access_time31-10-2026 remove_red_eye514 personAnita Karyati