End of November, Latumenten Crossing Channel Construction Completed

It is done, as it was too small and could not handle puddles on Jalan Satria IV maximally

The progress of crossing channel construction works on Jalan Latumenten, Grogol Petamburan, West Jakarta has reached 75 percent.

Development and Drainage Improvement Division Head Imam Prastyo said the channel that would have 31 meters long with 2 meters width and 2 meters height had been carried out since October 13.

Prevent Flood, West Jakarta Continues to Take Anticipatory Actions

"It is done, as it was too small and could not handle puddles on Jalan Satria IV maximally," he said, Tuesday (11/10).

He added it was targeted to be complete by the end of this month.

Linked News
Popular News indeks
  1. Central Jakarta Administration Acts Swiftly to Handle Kebon Kosong Fire

    access_time02-06-2026 remove_red_eye1443 personFolmer
  2. Central Jakarta Government Responds Quickly to Fire Victims in Tanah Tinggi

    access_time04-06-2026 remove_red_eye974 personFolmer
  3. Jakarta Waives Motor Vehicle Tax Fines and Title Transfer Fees

    access_time01-06-2026 remove_red_eye879 personAldi Geri Lumban Tobing
  4. Traffic Measures Prepared to Ease Congestion Around GBK This Weekend

    access_time04-06-2026 remove_red_eye770 personAldi Geri Lumban Tobing
  5. Public Urged to Use Public Transit for GBK Events to Avoid Heavy Traffic

    access_time05-06-2026 remove_red_eye682 personAldi Geri Lumban Tobing