End of November, Latumenten Crossing Channel Construction Completed

It is done, as it was too small and could not handle puddles on Jalan Satria IV maximally

The progress of crossing channel construction works on Jalan Latumenten, Grogol Petamburan, West Jakarta has reached 75 percent.

Development and Drainage Improvement Division Head Imam Prastyo said the channel that would have 31 meters long with 2 meters width and 2 meters height had been carried out since October 13.

Prevent Flood, West Jakarta Continues to Take Anticipatory Actions

"It is done, as it was too small and could not handle puddles on Jalan Satria IV maximally," he said, Tuesday (11/10).

He added it was targeted to be complete by the end of this month.

Linked News
Popular News indeks
  1. Pramono Launches Jumbo Biopores, Aims for Jakarta Waste Management Blueprint

    access_time07-06-2026 remove_red_eye1005 personDessy Suciati
  2. Transjakarta Adjusts Operations Due to Public Demonstration

    access_time12-06-2026 remove_red_eye997 personAldi Geri Lumban Tobing
  3. Pramono: Transjabodetabek Fare Adjustment Based on Careful Consideration

    access_time10-06-2026 remove_red_eye982 personDessy Suciati
  4. BTN JAKIM 2026, Traffic Engineering and Alternative Routes Provided

    access_time11-06-2026 remove_red_eye770 personAldi Geri Lumban Tobing
  5. Accelerating Jakarta`s Global City Development, Pramono Inaugurates Urban Knowledge Hub

    access_time08-06-2026 remove_red_eye651 personDessy Suciati