End of November, Latumenten Crossing Channel Construction Completed

It is done, as it was too small and could not handle puddles on Jalan Satria IV maximally

The progress of crossing channel construction works on Jalan Latumenten, Grogol Petamburan, West Jakarta has reached 75 percent.

Development and Drainage Improvement Division Head Imam Prastyo said the channel that would have 31 meters long with 2 meters width and 2 meters height had been carried out since October 13.

Prevent Flood, West Jakarta Continues to Take Anticipatory Actions

"It is done, as it was too small and could not handle puddles on Jalan Satria IV maximally," he said, Tuesday (11/10).

He added it was targeted to be complete by the end of this month.

Linked News
Popular News indeks
  1. Commission D Legislator Supports Park Monitoring Optimization

    access_time20-01-2025 remove_red_eye1524 personDessy Suciati
  2. Realizing Food Self-Sufficiency, Jakarta Holds Simultaneous Planting Activity

    access_time21-01-2025 remove_red_eye943 personAldi Geri Lumban Tobing
  3. Gulkarmat to Intensify Fire Mitigation Education

    access_time22-01-2025 remove_red_eye474 personBudhi Firmansyah Surapati
  4. BMKG Warns of Potential High Rainfall in Jakarta

    access_time22-01-2025 remove_red_eye432 personDessy Suciati
  5. City and Kejati Forge Cooperation for Good Government Governance

    access_time21-01-2025 remove_red_eye412 personFolmer