End of November, Latumenten Crossing Channel Construction Completed

It is done, as it was too small and could not handle puddles on Jalan Satria IV maximally

The progress of crossing channel construction works on Jalan Latumenten, Grogol Petamburan, West Jakarta has reached 75 percent.

Development and Drainage Improvement Division Head Imam Prastyo said the channel that would have 31 meters long with 2 meters width and 2 meters height had been carried out since October 13.

Prevent Flood, West Jakarta Continues to Take Anticipatory Actions

"It is done, as it was too small and could not handle puddles on Jalan Satria IV maximally," he said, Tuesday (11/10).

He added it was targeted to be complete by the end of this month.

Linked News
Popular News indeks
  1. Jakarta Taps MSMEs and Creative Economy to Secure Global Top 50 Spot

    access_time11-07-2026 remove_red_eye1717 personAldi Geri Lumban Tobing
  2. Pramono will Take Firm Action Against Individuals Involved in Extortion

    access_time13-07-2026 remove_red_eye1129 personDessy Suciati
  3. The Pegangsaan Dua-Manggarai LRT Project Reaches 95 Percent Completion

    access_time14-07-2026 remove_red_eye821 personDessy Suciati
  4. North Jakarta KPKP is Intensively Monitoring Animal Health Service Licensing

    access_time16-07-2026 remove_red_eye783 personAnita Karyati
  5. SDN Srengseng Sawah 15 Continues Face-to-Face Learning

    access_time13-07-2026 remove_red_eye712 personDessy Suciati