 Pembangunan Crossingan Latumenten Sudah 75 Persen

End of November, Latumenten Crossing Channel Construction Completed

It is done, as it was too small and could not handle puddles on Jalan Satria IV maximally

The progress of crossing channel construction works on Jalan Latumenten, Grogol Petamburan, West Jakarta has reached 75 percent.

Development and Drainage Improvement Division Head Imam Prastyo said the channel that would have 31 meters long with 2 meters width and 2 meters height had been carried out since October 13.

Prevent Flood, West Jakarta Continues to Take Anticipatory Actions

"It is done, as it was too small and could not handle puddles on Jalan Satria IV maximally," he said, Tuesday (11/10).

He added it was targeted to be complete by the end of this month.

Linked News
Popular News indeks
  1. City Council Strengthens Synergy with Central Legislators to Support Jakarta`s Development

    access_time30-07-2026 remove_red_eye1039 personFakhrizal Fakhri
  2. Jakarta Government Prepares Rp 249 B to Renovate Four Schools

    access_time25-07-2026 remove_red_eye877 personDessy Suciati
  3. Rano Urges Jakarta Scouts to Be Active in Waste Sorting Movement

    access_time25-07-2026 remove_red_eye691 personAldi Geri Lumban Tobing
  4. Pramono Encourages Residents to Stay Active at Rasuna Said CFD

    access_time26-07-2026 remove_red_eye622 personFolmer
  5. Jakarta Steps Up Food Waste Prevention

    access_time25-07-2026 remove_red_eye572 personAldi Geri Lumban Tobing