End of November, Latumenten Crossing Channel Construction Completed

It is done, as it was too small and could not handle puddles on Jalan Satria IV maximally

The progress of crossing channel construction works on Jalan Latumenten, Grogol Petamburan, West Jakarta has reached 75 percent.

Development and Drainage Improvement Division Head Imam Prastyo said the channel that would have 31 meters long with 2 meters width and 2 meters height had been carried out since October 13.

Prevent Flood, West Jakarta Continues to Take Anticipatory Actions

"It is done, as it was too small and could not handle puddles on Jalan Satria IV maximally," he said, Tuesday (11/10).

He added it was targeted to be complete by the end of this month.

Linked News
Popular News indeks
  1. Pramono Vows to Prioritize Jakarta’s Strategic Development

    access_time22-08-2026 remove_red_eye1034 personDessy Suciati
  2. Rano: CIEIE 2026 to Catapult Jakarta’s MSMEs onto the International Stage

    access_time25-08-2026 remove_red_eye741 personBudhi Firmansyah Surapati
  3. Jakarta Deploys 120 Personnel to Counteract Traffic Disruption for Today’s Protests

    access_time27-08-2026 remove_red_eye694 personAldi Geri Lumban Tobing
  4. Pramono Pushes for Partnership Between New Toto Tentrem and Tarakan Hospitals

    access_time24-08-2026 remove_red_eye659 personDessy Suciati
  5. New LRT Jakarta Route Set for Official Launch on August 26

    access_time22-08-2026 remove_red_eye516 personDessy Suciati