End of November, Latumenten Crossing Channel Construction Completed

It is done, as it was too small and could not handle puddles on Jalan Satria IV maximally

The progress of crossing channel construction works on Jalan Latumenten, Grogol Petamburan, West Jakarta has reached 75 percent.

Development and Drainage Improvement Division Head Imam Prastyo said the channel that would have 31 meters long with 2 meters width and 2 meters height had been carried out since October 13.

Prevent Flood, West Jakarta Continues to Take Anticipatory Actions

"It is done, as it was too small and could not handle puddles on Jalan Satria IV maximally," he said, Tuesday (11/10).

He added it was targeted to be complete by the end of this month.

Linked News
Popular News indeks
  1. Indonesia-Singapore Match: 80 Dishub Personnel Deployed to Manage Traffic Around GBK

    access_time25-09-2026 remove_red_eye590 personAldi Geri Lumban Tobing
  2. Jakarta International Stadium Sets Up Transit Schemes for The Weeknd Concert

    access_time24-09-2026 remove_red_eye472 personAldi Geri Lumban Tobing
  3. Jakarta Calls on Residents to Save Energy with 60-Minute Lights-Off Action

    access_time19-09-2026 remove_red_eye433 personAldi Geri Lumban Tobing
  4. South Jakarta BPBD Distributes 44,000 Liters of Clean Water

    access_time19-09-2026 remove_red_eye371 personTiyo Surya Sakti
  5. Jakarta Inspectorate Partners with KPK to Foster Early Anti-Corruption Culture

    access_time20-09-2026 remove_red_eye322 personFolmer