 Pembangunan Crossingan Latumenten Sudah 75 Persen

End of November, Latumenten Crossing Channel Construction Completed

It is done, as it was too small and could not handle puddles on Jalan Satria IV maximally

The progress of crossing channel construction works on Jalan Latumenten, Grogol Petamburan, West Jakarta has reached 75 percent.

Development and Drainage Improvement Division Head Imam Prastyo said the channel that would have 31 meters long with 2 meters width and 2 meters height had been carried out since October 13.

Prevent Flood, West Jakarta Continues to Take Anticipatory Actions

"It is done, as it was too small and could not handle puddles on Jalan Satria IV maximally," he said, Tuesday (11/10).

He added it was targeted to be complete by the end of this month.

Linked News
Popular News indeks
  1. Jakarta Announces Rp 1 Fare for Transjakarta, MRT, and LRT on August 17

    access_time13-08-2026 remove_red_eye888 personAldi Geri Lumban Tobing
  2. Abdul Muis Building Fire Response Nears Completion, No Fatalities Reported

    access_time08-08-2026 remove_red_eye598 personAldi Geri Lumban Tobing
  3. Pramono Urges MUI to Strengthen Synergy in Maintaining Jakarta’s Harmony

    access_time12-08-2026 remove_red_eye574 personDessy Suciati
  4. Jakarta Ensures Public Services Stay Operational After Abdul Muis Building Fire

    access_time08-08-2026 remove_red_eye562 personFakhrizal Fakhri
  5. Fire Site in Utan Kayu Utara Being Cleared

    access_time11-08-2026 remove_red_eye422 personNurito