 Pembangunan Crossingan Latumenten Sudah 75 Persen

End of November, Latumenten Crossing Channel Construction Completed

It is done, as it was too small and could not handle puddles on Jalan Satria IV maximally

The progress of crossing channel construction works on Jalan Latumenten, Grogol Petamburan, West Jakarta has reached 75 percent.

Development and Drainage Improvement Division Head Imam Prastyo said the channel that would have 31 meters long with 2 meters width and 2 meters height had been carried out since October 13.

Prevent Flood, West Jakarta Continues to Take Anticipatory Actions

"It is done, as it was too small and could not handle puddles on Jalan Satria IV maximally," he said, Tuesday (11/10).

He added it was targeted to be complete by the end of this month.

Linked News
Popular News indeks
  1. Open for All: Jakarta City Hall Welcomes Visitors for Namu Balai Kota

    access_time03-10-2026 remove_red_eye784 personDessy Suciati
  2. 1,500 Runners and Pets Hit the Track for World Rabies Day Run 2026

    access_time03-10-2026 remove_red_eye577 personAnita Karyati
  3. Jakarta Logs 0.13% Inflation as Chicken, Chili, and Rice Push Prices Up

    access_time03-10-2026 remove_red_eye546 personFakhrizal Fakhri
  4. Don’t Miss Out! The 17th Palang Pintu Festival Takes Over Jalan Kemang Raya

    access_time03-10-2026 remove_red_eye508 personTiyo Surya Sakti
  5. Jakarta Administration Steps Up Proactive Fire Prevention Efforts

    access_time09-10-2026 remove_red_eye366 personDessy Suciati