 Pembangunan Crossingan Latumenten Sudah 75 Persen

End of November, Latumenten Crossing Channel Construction Completed

It is done, as it was too small and could not handle puddles on Jalan Satria IV maximally

The progress of crossing channel construction works on Jalan Latumenten, Grogol Petamburan, West Jakarta has reached 75 percent.

Development and Drainage Improvement Division Head Imam Prastyo said the channel that would have 31 meters long with 2 meters width and 2 meters height had been carried out since October 13.

Prevent Flood, West Jakarta Continues to Take Anticipatory Actions

"It is done, as it was too small and could not handle puddles on Jalan Satria IV maximally," he said, Tuesday (11/10).

He added it was targeted to be complete by the end of this month.

Linked News
Popular News indeks
  1. Jakarta Council Begins Deliberations on New Population and Housing Bylaws

    access_time21-08-2026 remove_red_eye912 personFakhrizal Fakhri
  2. Jakarta Assesses Needs and Coordinates Aid for NTT Earthquake Victims

    access_time16-08-2026 remove_red_eye726 personAldi Geri Lumban Tobing
  3. 21 Parking Locations Prepared for Indonesian Independence Day Celebrations

    access_time15-08-2026 remove_red_eye720 personAldi Geri Lumban Tobing
  4. Jakarta Prepares Aid for NTT Earthquake Victims

    access_time16-08-2026 remove_red_eye678 personDessy Suciati
  5. Pramono: Independence must Be Manifested Through Concrete Action

    access_time17-08-2026 remove_red_eye674 personDessy Suciati