Connecting Channel Dredging around Taman Ratu Has Touched 70 Percent

The dredging work process in the Taman Ratu connecting channel, Kedoya, Kebon Jeruk has touched 70 percent. 

This is our way to handle puddles and floods around the Taman Ratu area

West Jakarta Water Resources (SDA) Sub-agency's Clean Water, Water Raw and Water Flood Control Systems Division Head Wawan said that it had been carried out since October 22 and was targeted to be complete within two weeks ahead.

"To conduct it, we have sent two heavy equipment to the location. Thus far we have transported 300 cubic meter of mud," he expressed, Tuesday (11/17).

Central Jakarta Continues to Optimize Flood Mitigation

He added it was one of efforts to maximize the channel in accommodating the water in the current rainy season.

"This is our way to handle puddles and floods around the Taman Ratu area," he stated.

Linked News
Popular News indeks
  1. Takjil Supervision in Central Jakarta Begins Second Week

    access_time02-03-2025 remove_red_eye469 personBudhi Firmansyah Surapati
  2. Government Declares Ramadhan Starts on March 1, 2025

    access_time28-02-2025 remove_red_eye443 personBudhi Firmansyah Surapati
  3. Dishub: Lay Bay Remains Optimal to Support Public Transportation User Comfort

    access_time02-03-2025 remove_red_eye396 personAldi Geri Lumban Tobing
  4. Traffic Diverted on Jalan Jatinegara Barat as Floods Hit Jakarta

    access_time04-03-2025 remove_red_eye368 personNurito
  5. City Government Ensures Pondok Bambu Fire Survivors Needs are Met

    access_time01-03-2025 remove_red_eye331 personNurito

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik