Repair work on channel's retaining wall on Jl. Pramuka, Matraman, East Jakarta has reached 30 percent.
Currently, repair process has reached 30 percent and it is targeted to finish in mid December
Matraman Water Resources (SDA) Unit Coordinator, Agus mentioned, his side manyally repaired two parts of retaining wall which collapsed as long as 15 meters and 8 meters.
"Currently, repair process has reached 30 percent and it is targeted to finish in mid December
," he explained, Monday (11/23).Channels on Jalan Taman Wijaya Kusuma Being CleanedThe main obstacle in this repairing, he continued, is many utilities inside the channel.