Perbaikan Turap Saluran Air di Jl Pramuka Capai 30 Persen

Channel's Retaining Wall Repair on Jl. Pramuka Touches 30 Percent

Repair work on channel's retaining wall on Jl. Pramuka, Matraman, East Jakarta has reached 30 percent.

Currently, repair process has reached 30 percent and it is targeted to finish in mid December

Matraman Water Resources (SDA) Unit Coordinator, Agus mentioned, his side manyally repaired two parts of retaining wall which collapsed as long as 15 meters and 8 meters.

"Currently, repair process has reached 30 percent and it is targeted to finish in mid December," he explained, Monday (11/23).

Channels on Jalan Taman Wijaya Kusuma Being Cleaned

The main obstacle in this repairing, he continued, is many utilities inside the channel.

"But we will accelerate the repair to ensure it finished on time," he asserted.

Linked News
Popular News indeks
  1. City Council Strengthens Synergy with Central Legislators to Support Jakarta`s Development

    access_time30-07-2026 remove_red_eye1084 personFakhrizal Fakhri
  2. Jakarta Partners with Five Satellite Cities for Greater Jakarta Connected Initiative

    access_time30-07-2026 remove_red_eye611 personBudhi Firmansyah Surapati
  3. Still Rp 3,500! No Fare Change for Transjakarta’s Kalideres–Soetta Route

    access_time01-08-2026 remove_red_eye522 personAldi Geri Lumban Tobing
  4. Jakarta Reaffirms Commitment to Preserving Cultural Heritage

    access_time31-07-2026 remove_red_eye501 personDessy Suciati
  5. Various Events Prepared for Jakarta`s 5th Century Anniversary

    access_time29-07-2026 remove_red_eye481 personFakhrizal Fakhri