Pembangunan Saluran Phb di Jl Mayjen Soetoto Capai 74,58 Persen

Phb Channel Construction on Jl. Mayjen Soetoyo Touches 74.58 Percent

Connecting (phb) channel is being built on Jl. Mayjen Soetoyo, Cililitan Urban Village, Kramatjati, East Jakarta. Its process now has reached 74.58 percent.

This work is targeted to finish by the end of December

East Jakarta Water Resources (SDA) Development and Drainage Improvement Section Head, Tengku Saugi Zikri conveyed, this 280-meter channel is one of 11 channels which are being built in East Jakarta.

"So far, channel construction on Jl. Mayjen Soetoyo has reached 74.58 percent," he explained, Tuesday (11/24).

Channel's Retaining Wall Repair on Jl. Pramuka Touches 30 Percent

According to him, this channel is built from in front of SPBU Cililitan until RW 14 Cililitan, in front of National Legal Development Agency (BPHN) Office of Law and Human Rights Ministry.

"This work is targeted to finish by the end of December," he stated.

Linked News
Popular News indeks
  1. Pram-Rano Attend Bung Karno Festival at Proklamasi Park

    access_time20-06-2026 remove_red_eye1092 personFolmer
  2. JIS-Ancol Integrated Infrastructure Officially Activated

    access_time23-06-2026 remove_red_eye575 personDessy Suciati
  3. Free Cake-Making Training Held at RPTRA Mustika Ratu

    access_time23-06-2026 remove_red_eye500 personNurito
  4. Metropolitan City Rally 2026 to Be Held at City Hall

    access_time19-06-2026 remove_red_eye480 personAldi Geri Lumban Tobing
  5. Rano Officially Opens Discover Betawi Art and Culture 2026

    access_time19-06-2026 remove_red_eye476 personBudhi Firmansyah Surapati