End of January, Dredging Work on Tomang Reservoir Completed
access_time January 08 2021 05:56 PM remove_red_eye 721
Reported by Rudi Hermawan | Translated by Nugroho Adibrata
Reported by Rudi Hermawan | Translated by Nugroho Adibrata
To smoothen the work, we have alerted eight personnel, two heavy equipment namely two amphibious excavators and one long arm
The dredging work on Tomang Barat Reservoir, Tanjung Duren Utara, Grogol Petamburan, West Jakarta is targeted to be completed by the end of this January.
West Jakarta Water Resources (SDA) Sub-agency Head Purwanti Suryandari said it had been carried out since the end of July and now has touched 90 percent.
Bojong Reservoir Dredging Work Has Reached 80 Percent"To smoothen the work, we have alerted eight personnel, two heavy equipment namely two amphibious excavators and one long arm," she stated, Friday (1/8).
There a
re also ten dump trucks to transport mud from the reservoir."This reservoir will be drilled up to three to four meters according to the existing one," she stated.