Bojong Reservoir Dredging Targeted to Finish By the End of This Month
access_time December 01 2020 07:34 PM remove_red_eye 1053
Reported by Rudi Hermawan | Translated by Maria Inggita
Reported by Rudi Hermawan | Translated by Maria Inggita
West Jakarta Water Resources (SDA) Sub-agency accelerates mud dredging work in Bojong Reservoir on Jalana Telaga Bojong, Rawa Buaya, Cengkareng, West Jakarta.
We carry out the work from November 17 and target it to finish by the end of December
"We carry out the work from November 17 and target it to finish by the end of December," conveyed Wawan Kurniawan, SDA Sub-agency's Flood Control Maintenance System for Clean Water and Wastewater Section Head, on Tuesday (12/1).
His side deployed 2 heavy equipment with amphibious and long excavator type and 8 dump trucks to dredge mud from reservoir with depth of 3 meters and 1.6 hectares wide.
Mampang River Along Jl. Pondok Karya Dredged"We dredge the mud thus reservoir can drain water optimally to anticipate inundation in the surrounding area," he mentioned.