Progress of JGC Side C Reservoir Dredging Work Touches 50 Percent

Tuesday, January 12th 2021 Reporter: Nurito Translator: Maria Inggita 1090

Pengerukan Waduk Side C JGC Cakung Capai 50 Persen

(Foto: Nurito)

Dredging work on Side C Reservoir in Jakarta Garden City (JGC), Jl. Koridor BKT, RW 07, Cakung Timur, Cakung, East Jakarta, has reached 50 percent.

Its progress has reached 50 percent and it is targeted to finish in the next two months

East Jakarta Water Resources (SDA) Sub-agency's Drainage Maintenance Section Head, Puryanto Palebangan stated, this reservoir dredging work which covers area about 22,030 square meters has been started on November 28, 2020 and targeted to complete in the next two months.

"Its progress has reached 50 percent and it is targeted to finish in the next two months," he said, Tuesday (1/12).

This reservoir, he informed, will have 2.5-3 meters deep. Currently, there are several points that already reached 1.5-2 meters deep.

For the dredging, his side deployed 11 heavy equipment from Jakarta SDA Agency's Alkal Unit with additional 1 big amphibious heavy equipment to clean water hyacinth.

His side also deployed 20 dump trucks to dispose excavated land to the East Flood Canal Sandtrep Area in Cakung and Ancol, North Jakarta.

"Side C Reservoir dredging work is carried out to overcome flood/inundation that occur on residential areas of RW 06, 07, and 08 Cakung Timur," he closed.