Normalisasi Kali Ciliwung Rampung Pertengahan November
Pengerjaan sejumlah proyek normalisasi kali untuk mencegah banjir di ibu kota terus dikebut. Salah satunya proyek normalisasi Kali Ciliwung di Jalan Matraman Raya, Kelurahan Kampung Melayu, Kecamatan Jatinegara yang dikerjakan Kementerian Pekerjaan .
photo Hendi Kusuma - Beritajakarta.id

Ciliwung River Normalization Project Accelerated

The normalization project of Ciliwung River on Jalan Matraman Raya, Kampung Melayu Urban Village, Jatinegara Sub-District, East Jakarta, carried out by the Public Works Ministry is accelerated. Now, the completion has reached 75 percent.

We will add workers from currently 50 men to 70 men to speed up the construction of the concrete wall

According to Head of Public Works Ministry Ciliwung-Cisadane Flood Control Office (BBWSCC), Dardi, the riverside is being reinforced with concrete for as long as 120 meters, 5 meters high, and 3.5 meters wide. The concrete’s function is to prevent water from overflowing and inundating residents’ settlements.

“The project’s completion process has reached 75 percent. Hopefully everything could finish this mid November. We will add workers from currently 50 men to 70 men to speed up the construction of the concrete wall,” he stated, Sunday (11/2).

5,150 Joint Personnel Clean Ciliwung River

Dardi admitted that this project got delayed because of some constraints, including the remnants of building’s foundation debris that had been demolished were difficult to be cleaned. The foundation of the building was stuck in the ground too deep, thus heavy equipment was used to remove it.

Linked News
Popular News indeks
  1. Transjakarta Targets Planting 100,000 Mangroves

    access_time12-07-2025 remove_red_eye414 personBudhi Firmansyah Surapati
  2. Rano Karno Celebrates City's Anniversary with Kamal Residents

    access_time12-07-2025 remove_red_eye395 personFolmer
  3. Residents Enthusiastically Enjoy the Car Free Day in Kebayoran Lama

    access_time13-07-2025 remove_red_eye352 personTiyo Surya Sakti
  4. Traffic Engineering on Jalan Otista to Begin July 20 Due to JPO Revitalization

    access_time17-07-2025 remove_red_eye324 personAldi Geri Lumban Tobing
  5. MRT Jakarta Considers Route Expansion to South Tangerang

    access_time13-07-2025 remove_red_eye316 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik