Sunter River Retaining Wall Repair Targeted to Finish in Mid-March

Repair work on collapsed Sunter River's retaining wall, RT 10/04 Pondok Bambu, Duren Sawit, East Jakarta that has been carried out since February is targeted to finish in mid-March.

We are targeting it to finish it in the next two weeks

Duren Saat Sub-district SDA Task Force Head, Achmad Dody Firmansyah mentioned, collapsed retaining wall that had to be repaired was about 14.5 meters long and 2.5 meters high. It collapsed due to flood on Tuesday (2/16). Currently the repair work progress has reached 30 percent.

"We repair it by installing stone gabions. We are targeting it to finish it in the next two weeks," he stated, Monday (3/1).

Residential Sheet Pile in Duri Selatan Repaired

His side deployed 9 SDA Task Force personnel to repair it which were sometimes also assisted by 5 PPSU personnel.

"Repair work sometimes hampered by rising water level of Sunter River during heavy rain," he said.

Linked News
Popular News indeks
  1. Jakarta and Lampung Collaborate to Launch Lampung-in App

    access_time15-06-2025 remove_red_eye440 personDessy Suciati
  2. Let's Celebrate Jakarta Future Festival 2025 at Taman Ismail Marzuki

    access_time11-06-2025 remove_red_eye417 personAldi Geri Lumban Tobing
  3. City Ready to Support Railway Transportation System in Bali

    access_time13-06-2025 remove_red_eye405 personBudhi Firmansyah Surapati
  4. Jakarta Future Festival 2025: Invitation to Contribute Developing Jakarta

    access_time12-06-2025 remove_red_eye395 personAldi Geri Lumban Tobing
  5. Cloudy Morning, Rainy Afternoon this Tuesday, BMKG Says

    access_time17-06-2025 remove_red_eye289 personDessy Suciati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik