Perbaikan Turap Longsor Kali Sunter Capai 30 Persen
.
photo Nurito - Beritajakarta.id

Sunter River Retaining Wall Repair Targeted to Finish in Mid-March

Repair work on collapsed Sunter River's retaining wall, RT 10/04 Pondok Bambu, Duren Sawit, East Jakarta that has been carried out since February is targeted to finish in mid-March.

We are targeting it to finish it in the next two weeks

Duren Saat Sub-district SDA Task Force Head, Achmad Dody Firmansyah mentioned, collapsed retaining wall that had to be repaired was about 14.5 meters long and 2.5 meters high. It collapsed due to flood on Tuesday (2/16). Currently the repair work progress has reached 30 percent.

"We repair it by installing stone gabions. We are targeting it to finish it in the next two weeks," he stated, Monday (3/1).

Residential Sheet Pile in Duri Selatan Repaired

His side deployed 9 SDA Task Force personnel to repair it which were sometimes also assisted by 5 PPSU personnel.

"Repair work sometimes hampered by rising water level of Sunter River during heavy rain," he said.

Linked News
Popular News indeks
  1. Duren Sawit PTSP Holds Door-to-Door Servies at Pondok Kelapa TPU until Thursday

    access_time15-05-2024 remove_red_eye696 personNurito
  2. Commission D: RDF Construction in Rorotan Has Many Benefits

    access_time13-05-2024 remove_red_eye579 personFolmer
  3. 35 Toddlers in Kedoya Selatan Received Assistance with Nutritious Additional Food

    access_time13-05-2024 remove_red_eye536 personTP Moan Simanjuntak
  4. Aiming to Global City, Jakarta Prioritizes the Development of Environmentally Friendly Waste Processing

    access_time13-05-2024 remove_red_eye534 personFolmer
  5. 42,878 Tourists Swarm Monas Area

    access_time12-05-2024 remove_red_eye375 personBudhi Firmansyah Surapati