You don't have javascript enabled. Good luck with that.
Pencarian
Perbaikan Turap Longsor Kali Sunter Capai 30 Persen

Sunter River Retaining Wall Repair Targeted to Finish in Mid-March

Repair work on collapsed Sunter River's retaining wall, RT 10/04 Pondok Bambu, Duren Sawit, East Jakarta that has been carried out since February is targeted to finish in mid-March.

We are targeting it to finish it in the next two weeks

Duren Saat Sub-district SDA Task Force Head, Achmad Dody Firmansyah mentioned, collapsed retaining wall that had to be repaired was about 14.5 meters long and 2.5 meters high. It collapsed due to flood on Tuesday (2/16). Currently the repair work progress has reached 30 percent.

"We repair it by installing stone gabions. We are targeting it to finish it in the next two weeks," he stated, Monday (3/1).

Residential Sheet Pile in Duri Selatan Repaired

His side deployed 9 SDA Task Force personnel to repair it which were sometimes also assisted by 5 PPSU personnel.

"Repair work sometimes hampered by rising water level of Sunter River during heavy rain," he said.

Linked News
Popular News indeks
  1. Cilandak Drainage Upgraded to Mitigate Flooding

    access_time27-01-2026 remove_red_eye869 personTiyo Surya Sakti
  2. TransJabodetabek Expansion, a Strategic Step to Increase Public Transportation Use

    access_time26-01-2026 remove_red_eye424 personFakhrizal Fakhri
  3. Jakarta Prepares OMC and 200 Excavators to Prevent Flood

    access_time26-01-2026 remove_red_eye371 personDessy Suciati
  4. Several Microtrans Routes Diverted

    access_time31-01-2026 remove_red_eye358 personAldi Geri Lumban Tobing
  5. Jakarta Showers to Make Way for Partly Cloudy Skies

    access_time30-01-2026 remove_red_eye358 personDessy Suciati
close