Sunter River Retaining Wall Repair Targeted to Finish in Mid-March

Repair work on collapsed Sunter River's retaining wall, RT 10/04 Pondok Bambu, Duren Sawit, East Jakarta that has been carried out since February is targeted to finish in mid-March.

We are targeting it to finish it in the next two weeks

Duren Saat Sub-district SDA Task Force Head, Achmad Dody Firmansyah mentioned, collapsed retaining wall that had to be repaired was about 14.5 meters long and 2.5 meters high. It collapsed due to flood on Tuesday (2/16). Currently the repair work progress has reached 30 percent.

"We repair it by installing stone gabions. We are targeting it to finish it in the next two weeks," he stated, Monday (3/1).

Residential Sheet Pile in Duri Selatan Repaired

His side deployed 9 SDA Task Force personnel to repair it which were sometimes also assisted by 5 PPSU personnel.

"Repair work sometimes hampered by rising water level of Sunter River during heavy rain," he said.

Linked News
Popular News indeks
  1. Immersive Room and Glowing Forest Attractions Enliven Eid at TMII

    access_time26-03-2026 remove_red_eye953 personFakhrizal Fakhri
  2. Jakarta Leaders Join Residents for Eid al-Fitr Prayer at City Hall

    access_time21-03-2026 remove_red_eye744 personFolmer
  3. 292 East Jakarta Personnel Mobilized for Eid Return Rush

    access_time25-03-2026 remove_red_eye734 personNurito
  4. Jakarta's Mudik to Jakarta Program Hits Rp21 Trillion in Transactions

    access_time25-03-2026 remove_red_eye724 personFakhrizal Fakhri
  5. 10 Transjakarta Amari Buses Operated at Kalideres Terminal

    access_time25-03-2026 remove_red_eye716 personTiyo Surya Sakti