Perbaikan Turap Longsor Kali Sunter Capai 30 Persen
.
photo Nurito - Beritajakarta.id

Sunter River Retaining Wall Repair Targeted to Finish in Mid-March

Repair work on collapsed Sunter River's retaining wall, RT 10/04 Pondok Bambu, Duren Sawit, East Jakarta that has been carried out since February is targeted to finish in mid-March.

We are targeting it to finish it in the next two weeks

Duren Saat Sub-district SDA Task Force Head, Achmad Dody Firmansyah mentioned, collapsed retaining wall that had to be repaired was about 14.5 meters long and 2.5 meters high. It collapsed due to flood on Tuesday (2/16). Currently the repair work progress has reached 30 percent.

"We repair it by installing stone gabions. We are targeting it to finish it in the next two weeks," he stated, Monday (3/1).

Residential Sheet Pile in Duri Selatan Repaired

His side deployed 9 SDA Task Force personnel to repair it which were sometimes also assisted by 5 PPSU personnel.

"Repair work sometimes hampered by rising water level of Sunter River during heavy rain," he said.

Linked News
Popular News indeks
  1. Deputy Gov Rano: Meat Stocks Secured Up to Ramadhan

    access_time22-02-2025 remove_red_eye532 personBudhi Firmansyah Surapati
  2. Jakarta to Hold Cheap Food Bazaar at 193 Locations

    access_time22-02-2025 remove_red_eye428 personBudhi Firmansyah Surapati
  3. Pramono - Rano Expected to Realize Better Resident Welfare

    access_time20-02-2025 remove_red_eye307 personBudhi Firmansyah Surapati
  4. Jakartans Invited to Participate in HPSN 2025 Event

    access_time21-02-2025 remove_red_eye297 personAldi Geri Lumban Tobing
  5. Jakarta Commits to Realizing National Waste Management Pilot Project

    access_time17-02-2025 remove_red_eye290 personFolmer