Perbaikan Turap Longsor Kali Sunter Capai 30 Persen
.
photo Nurito - Beritajakarta.id

Sunter River Retaining Wall Repair Targeted to Finish in Mid-March

Repair work on collapsed Sunter River's retaining wall, RT 10/04 Pondok Bambu, Duren Sawit, East Jakarta that has been carried out since February is targeted to finish in mid-March.

We are targeting it to finish it in the next two weeks

Duren Saat Sub-district SDA Task Force Head, Achmad Dody Firmansyah mentioned, collapsed retaining wall that had to be repaired was about 14.5 meters long and 2.5 meters high. It collapsed due to flood on Tuesday (2/16). Currently the repair work progress has reached 30 percent.

"We repair it by installing stone gabions. We are targeting it to finish it in the next two weeks," he stated, Monday (3/1).

Residential Sheet Pile in Duri Selatan Repaired

His side deployed 9 SDA Task Force personnel to repair it which were sometimes also assisted by 5 PPSU personnel.

"Repair work sometimes hampered by rising water level of Sunter River during heavy rain," he said.

Linked News
Popular News indeks
  1. Tanah Abang SDA Taskforce Normalizes Channels in Two Locations

    access_time12-05-2025 remove_red_eye466 personFolmer
  2. Community Work Held to Clean Environment in Petamburan

    access_time11-05-2025 remove_red_eye359 personFolmer
  3. Food Station Signs Farming Contracts in Rorotan

    access_time12-05-2025 remove_red_eye297 personAldi Geri Lumban Tobing
  4. Commission D Supports Construction of Rorotan Rusunawa

    access_time10-05-2025 remove_red_eye261 personFakhrizal Fakhri
  5. Pramono Focuses on Increasing Equal Access to Education

    access_time15-05-2025 remove_red_eye244 personDessy Suciati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik