You don't have javascript enabled. Good luck with that.
Pencarian
Ini Rekayasa Lalin Terkait Pembangunan Jembatan Penyeberangan Sepeda Karet Sudirman

Traffic Engineering will Be Implemented Due to Sudirman Bicycle Crossing Bridge Construction

Jakarta Transportation Agency implemented traffic engineering on Jalan Jenderal Sudirman, between Mayapada Tower and Le Meridien due to Karet Sudirman Bicycle Crossing Bridge (JPS).    

We implement traffic engineering according to the phase of work

Jakarta Transportation Agency Head, Syafrin Liputo mentioned, his side will first dismantle Transjakarta Karet Sudirman pedestrian crossing (JPO) before building JPS.

This construction work takes about 6 months to finish, from April 1 to September 2021. It includes dismantling roofs, ramp, as well as installing steel lifts, steel stairs, JPS floors and steel platforms.

MRT Jakarta Receives Award from MURI as the Most Bicycle Facility Provider

"In order to support it, we implement traffic engineering according to the phase of work," he said, Wednesday (3/31).

During the construction, Transjakarta Karet JPO users will be directed to use pelican crossing.

"We urge road users to avoid these roads and can follow the prevailing traffic regulations, traffic signs, instruction from officers on the field, and prioritize safety on the road," he asserted.

For information, here is traffic engineering which implemented according to phase of work;

- JPO demolishing work on west and east sides of Jalan Jenderal Sudirman on April 2-31, 2021 at 22.00-04.00. Two lanes will be closed.

-West JPS girder installation work on June 24, 2021 at 22.00-04.00:

• Traffic flow from south (Semanggi) to north (Bundaran HI) will be diverted to Jalan K.H. Mas Mansyur - U-turn - Jalan Karet Pasar Baru Timur 5 - Jalan Jenderal Sudirman;

• Traffic flow from north (Bundaran HI) to south (Semanggi) normal

- JPS structure and architecture installation work on west, east, and middle sides (median) from May 1 to August 16, 2021 at 22.00-04.00. Two lanes will be closed.

- East JPS girder installation on July 8, 2021 at 22.00-04.00:

• Traffic flow from north (Bundaran HI) to south (Semanggi) will be diverted to Landmark - Jalan Galunggung - Jalan RM. Margono Djojohadikoesoemo - Jalan K.H. Mansyur - Jalan Prof. Dr. Satrio - U-turn - Jalan Jenderal Sudirman.

• Traffic flow from south (Semanggi) to North (Bundaran HI) normal.

Linked News
Popular News indeks
  1. Rano Reaffirms Jakarta's Vision of Becoming a City of Cinema

    access_time22-10-2026 remove_red_eye5520 personBudhi Firmansyah Surapati
  2. Jakarta Provincial Government Receives a Grant of Rp 9.6 Billion in KPK`s Seized Assets

    access_time20-10-2026 remove_red_eye4658 personDessy Suciati
  3. Drainage Channels Along Two Rawajati Roads Dredged

    access_time21-10-2026 remove_red_eye1861 personTiyo Surya Sakti
  4. Check Saturday's Traffic Diversions for Jakarta Running Festival

    access_time23-10-2026 remove_red_eye858 personAldi Geri Lumban Tobing
  5. MRT Jakarta Prolongs Weekend Service for Kanye West Concert

    access_time23-10-2026 remove_red_eye756 personAldi Geri Lumban Tobing