Ini Rekayasa Lalin Terkait Pembangunan Jembatan Penyeberangan Sepeda Karet Sudirman
....
photo istimewa - Beritajakarta.id

Traffic Engineering will Be Implemented Due to Sudirman Bicycle Crossing Bridge Construction

Jakarta Transportation Agency implemented traffic engineering on Jalan Jenderal Sudirman, between Mayapada Tower and Le Meridien due to Karet Sudirman Bicycle Crossing Bridge (JPS).    

We implement traffic engineering according to the phase of work

Jakarta Transportation Agency Head, Syafrin Liputo mentioned, his side will first dismantle Transjakarta Karet Sudirman pedestrian crossing (JPO) before building JPS.

This construction work takes about 6 months to finish, from April 1 to September 2021. It includes dismantling roofs, ramp, as well as installing steel lifts, steel stairs, JPS floors and steel platforms.

MRT Jakarta Receives Award from MURI as the Most Bicycle Facility Provider

"In order to support it, we implement traffic engineering according to the phase of work," he said, Wednesday (3/31).

During the construction, Transjakarta Karet JPO users will be directed to use pelican crossing.

"We urge road users to avoid these roads and can follow the prevailing traffic regulations, traffic signs, instruction from officers on the field, and prioritize safety on the road," he asserted.

For information, here is traffic engineering which implemented according to phase of work;

- JPO demolishing work on west and east sides of Jalan Jenderal Sudirman on April 2-31, 2021 at 22.00-04.00. Two lanes will be closed.

-West JPS girder installation work on June 24, 2021 at 22.00-04.00:

• Traffic flow from south (Semanggi) to north (Bundaran HI) will be diverted to Jalan K.H. Mas Mansyur - U-turn - Jalan Karet Pasar Baru Timur 5 - Jalan Jenderal Sudirman;

• Traffic flow from north (Bundaran HI) to south (Semanggi) normal

- JPS structure and architecture installation work on west, east, and middle sides (median) from May 1 to August 16, 2021 at 22.00-04.00. Two lanes will be closed.

- East JPS girder installation on July 8, 2021 at 22.00-04.00:

• Traffic flow from north (Bundaran HI) to south (Semanggi) will be diverted to Landmark - Jalan Galunggung - Jalan RM. Margono Djojohadikoesoemo - Jalan K.H. Mansyur - Jalan Prof. Dr. Satrio - U-turn - Jalan Jenderal Sudirman.

• Traffic flow from south (Semanggi) to North (Bundaran HI) normal.

Linked News
Popular News indeks
  1. Mothers Attack Cheap Market in Cibubur Urban Village

    access_time02-05-2024 remove_red_eye632 personNurito
  2. S. Jakarta Residents Enjoy NIK Deactivation Consultation Post Services in Rawajati

    access_time30-04-2024 remove_red_eye423 personTiyo Surya Sakti
  3. Sunny All Day Long in Jakarta

    access_time03-05-2024 remove_red_eye384 personAnita Karyati
  4. Secretariat General Bureau-Information Commission Holds E-Monev Bimtek 2024

    access_time28-04-2024 remove_red_eye348 personAnita Karyati
  5. Immunization Held in Lebak Bulus Urban Village

    access_time29-04-2024 remove_red_eye292 personTiyo Surya Sakti