Ini Rekayasa Lalin Terkait Pembangunan Jembatan Penyeberangan Sepeda Karet Sudirman

Traffic Engineering will Be Implemented Due to Sudirman Bicycle Crossing Bridge Construction

Jakarta Transportation Agency implemented traffic engineering on Jalan Jenderal Sudirman, between Mayapada Tower and Le Meridien due to Karet Sudirman Bicycle Crossing Bridge (JPS).    

We implement traffic engineering according to the phase of work

Jakarta Transportation Agency Head, Syafrin Liputo mentioned, his side will first dismantle Transjakarta Karet Sudirman pedestrian crossing (JPO) before building JPS.

This construction work takes about 6 months to finish, from April 1 to September 2021. It includes dismantling roofs, ramp, as well as installing steel lifts, steel stairs, JPS floors and steel platforms.

MRT Jakarta Receives Award from MURI as the Most Bicycle Facility Provider

"In order to support it, we implement traffic engineering according to the phase of work," he said, Wednesday (3/31).

During the construction, Transjakarta Karet JPO users will be directed to use pelican crossing.

"We urge road users to avoid these roads and can follow the prevailing traffic regulations, traffic signs, instruction from officers on the field, and prioritize safety on the road," he asserted.

For information, here is traffic engineering which implemented according to phase of work;

- JPO demolishing work on west and east sides of Jalan Jenderal Sudirman on April 2-31, 2021 at 22.00-04.00. Two lanes will be closed.

-West JPS girder installation work on June 24, 2021 at 22.00-04.00:

• Traffic flow from south (Semanggi) to north (Bundaran HI) will be diverted to Jalan K.H. Mas Mansyur - U-turn - Jalan Karet Pasar Baru Timur 5 - Jalan Jenderal Sudirman;

• Traffic flow from north (Bundaran HI) to south (Semanggi) normal

- JPS structure and architecture installation work on west, east, and middle sides (median) from May 1 to August 16, 2021 at 22.00-04.00. Two lanes will be closed.

- East JPS girder installation on July 8, 2021 at 22.00-04.00:

• Traffic flow from north (Bundaran HI) to south (Semanggi) will be diverted to Landmark - Jalan Galunggung - Jalan RM. Margono Djojohadikoesoemo - Jalan K.H. Mansyur - Jalan Prof. Dr. Satrio - U-turn - Jalan Jenderal Sudirman.

• Traffic flow from south (Semanggi) to North (Bundaran HI) normal.

Linked News
Popular News indeks
  1. Jakarta Endorses New Housing Project for Residents on Railway Embankments

    access_time28-03-2026 remove_red_eye2399 personDessy Suciati
  2. Pramono Affirms Commitment to Enhancing Regional Financial Management Quality

    access_time02-04-2026 remove_red_eye782 personTiyo Surya Sakti
  3. Pramono Calls for Enhanced Synergy at DPRD Post-Eid Gathering

    access_time30-03-2026 remove_red_eye692 personDessy Suciati
  4. Banners Prohibiting Illegal Parking Levies Installed at Blok M Square

    access_time02-04-2026 remove_red_eye628 personTiyo Surya Sakti
  5. Jakarta Environmental Sub-agency Clears Trash Buildup at Kramat Jati Wholesale Market

    access_time28-03-2026 remove_red_eye460 personNurito