 Pembangunan Embung di Cempaka Mas Capai 70 Persen

After Eid, First Phase Embung Development in Cempaka Mas Completed

It is targeted to be complete after Eid ul Fitr

The embung (artificial lake) development in the first phase, which is located in the Cempaka Mas ITC area, Jalan Letjen Suprapto, Central Jakarta has so far progressed to 70 percent.

Central Jakarta Water Resources (SDA) Sub-agency's Maintenance Division Head, Achmad Daeroby disclosed it was built on a 1,000-square-meter land.

Flamboyan Embung Project Work in Cengkareng Accelerated

He expressed that the project work was under control by the Central Jakarta SDA Sub-agency, starting from the provision of heavy equipment, materials and workers.

"It is targeted to be complete after Eid ul Fitr," he expressed, Thursday (4/15).

The second phase would be built on a 1,500-square-meter land and was still under planning process.

"The embung itself is designed to have a large capacity to accommodate rainwater which often inundates Jalan Letjen Suprapto," he closed.

Linked News
Popular News indeks
  1. Jakarta Taps MSMEs and Creative Economy to Secure Global Top 50 Spot

    access_time11-07-2026 remove_red_eye1606 personAldi Geri Lumban Tobing
  2. Ciliwung River Normalization Accelerated, Pramono Ensures Land Acquisition Without Intermediaries

    access_time10-07-2026 remove_red_eye1452 personDessy Suciati
  3. Blocked Drain on Jalan Palmerah Utara is Being Repaired

    access_time10-07-2026 remove_red_eye1318 personFolmer
  4. Pramono will Take Firm Action Against Individuals Involved in Extortion

    access_time13-07-2026 remove_red_eye1088 personDessy Suciati
  5. Pramono Inaugurates Mayapada Hospital to Improve Healthcare Services

    access_time09-07-2026 remove_red_eye977 personDessy Suciati