Channel Repair on Jl. Flamboyan Kebon Jeruk Has Reached 80 Percent

West Jakarta Water Resources (SDA) Sub-agency is currently repaired water channel on Jl. Flamboyan, Kebon Jeruk, by installing it with U-ditch and covers.

Our target is to complete it by the end of June

West Jakarta SDA Sub-agency Drainage Maintenance Section Head, Wawan Kurniawan mentioned, U-ditch and covers installation work has been carried out since June 12, 2021.  

"U-ditch and channel covers will be installed on channel along 80 meters with width 60 centimeters," he informed, Thursday (6/24).

Channel on Jalan Merpati in Meruya Utara Widened

His side deployed 1 unit mini excavator and 13 personnel equipped with hoes, crowbars, sledgehammers, hammers, and buckets.

"Current progress has reached 80 percent. Our target is to complete it by the end of June," he said.

He hopes this repair can optimize water channel capacity thus it can minimize inundation, especially during heavy rains.

Linked News
Popular News indeks
  1. Commission E Urges Residents to Increase Role in Preventing DHF

    access_time19-12-2024 remove_red_eye1205 personDessy Suciati
  2. Transjakarta Adjusting Service as Simpang Pramuka and Rawamangun Bus Stops Closed

    access_time18-12-2024 remove_red_eye1050 personAldi Geri Lumban Tobing
  3. Transjakarta, Telkomsel to Improve Service for Customers

    access_time19-12-2024 remove_red_eye903 personAldi Geri Lumban Tobing
  4. Acting Governor Monitors Food Stock at Kramat Jati and Cipinang Markets

    access_time19-12-2024 remove_red_eye728 personFolmer
  5. Jakarta Provincial Government Holds Christmas Carol

    access_time18-12-2024 remove_red_eye569 personDessy Suciati