Cilangkap Reservoir Dredging Progress Reaches 35 Percent

It is carried out to overcome inundation in Cilangkap, Setu, Bambu Apus, etc

The dredging progress of the Cilangkap Reservoir at RW 01 Cilangkap, Cipayung, East Jakarta, has now reached 35 percent.

East Jakarta Water Resources (SDA) Sub-agency's Maintenance Division Head, Puryanto said, the reservoir was dredged to four to five meters depth using four heavy equipment consisting of one long arm and three standard units.

East Jakarta SDA will Dredge Reservoirs, Rivers, and Phb Channels in 14 Additional Locations

"It is carried out to overcome inundation in Cilangkap, Setu, Bambu Apus, etc," he expressed, Friday (9/24).

To smoothen it, the water in the reservoir was drained by closing the sluice gate bordering the reservoir in the Cilangkap Agro Tourism area.

He explained, the dredged mud was used to build inspection roads on the left and right of the reservoir with five meters width.

"It is expected to be completed by the end of this year," he stated.

Linked News
Popular News indeks
  1. Jakarta to Host World Cities Culture Summit 2027

    access_time31-10-2026 remove_red_eye628 personBudhi Firmansyah Surapati
  2. Road to Larata Run 2026 Combines Running with Public Transport

    access_time31-10-2026 remove_red_eye549 personAnita Karyati
  3. Faith Meets Progress, Ancol Prayer Gathering Fortifies Jakarta’s Journey as a Global City

    access_time01-11-2026 remove_red_eye379 personAnita Karyati
  4. House Fire in Sunter Agung Successfully Extinguished

    access_time04-11-2026 remove_red_eye369 personAnita Karyati
  5. Brunei Darussalam Delegation Invited to Explore Jakarta`s Marine Tourism Destinations

    access_time02-11-2026 remove_red_eye341 personAldi Geri Lumban Tobing