Cilangkap Reservoir Dredging Progress Reaches 35 Percent

It is carried out to overcome inundation in Cilangkap, Setu, Bambu Apus, etc

The dredging progress of the Cilangkap Reservoir at RW 01 Cilangkap, Cipayung, East Jakarta, has now reached 35 percent.

East Jakarta Water Resources (SDA) Sub-agency's Maintenance Division Head, Puryanto said, the reservoir was dredged to four to five meters depth using four heavy equipment consisting of one long arm and three standard units.

East Jakarta SDA will Dredge Reservoirs, Rivers, and Phb Channels in 14 Additional Locations

"It is carried out to overcome inundation in Cilangkap, Setu, Bambu Apus, etc," he expressed, Friday (9/24).

To smoothen it, the water in the reservoir was drained by closing the sluice gate bordering the reservoir in the Cilangkap Agro Tourism area.

He explained, the dredged mud was used to build inspection roads on the left and right of the reservoir with five meters width.

"It is expected to be completed by the end of this year," he stated.

Linked News
Popular News indeks
  1. Rano: CIEIE 2026 to Catapult Jakarta’s MSMEs onto the International Stage

    access_time25-08-2026 remove_red_eye755 personBudhi Firmansyah Surapati
  2. Jakarta Deploys 120 Personnel to Counteract Traffic Disruption for Today’s Protests

    access_time27-08-2026 remove_red_eye738 personAldi Geri Lumban Tobing
  3. Pramono Pushes for Partnership Between New Toto Tentrem and Tarakan Hospitals

    access_time24-08-2026 remove_red_eye669 personDessy Suciati
  4. Transjakarta Commits to Transport Equality Across the Seribu Islands

    access_time24-08-2026 remove_red_eye604 personAldi Geri Lumban Tobing
  5. Transjakarta Resumes Operations with Strategic Service Adjustments

    access_time28-08-2026 remove_red_eye580 personAldi Geri Lumban Tobing