This Week, Sheet Pile Elevation on Jalan Asri 1 Completed
access_time October 03 2023 04:31 PM remove_red_eye 404
Reported by Budhi Firmansyah Surapati | Translated by Nugroho Adibrata
Reported by Budhi Firmansyah Surapati | Translated by Nugroho Adibrata
The 50-centimeter-high sheet pile elevation on Jalan Pelepah Asri 1, Janur Asri Housing Complex, RW 12 Kelapa Gading Barat Urban Village, Kelapa Gading, which has been underway since September 7 is targeted for completion this week.
This work involves eight personnel every day
Kelapa Gading Water Resources (SDA) Executing Unit Head, Citrin Indarwati said the sheet pile was elevated to 70 centimeters high.
"This work involves eight personnel every day," she expressed.
Collapsed Sheet Pile on Jalan Puri Kembangan RepairedAccording to him, the sheet pile has a length of 86 meters and a width of 40 centimeters.
"Thus far, the work progress has touched 95 percent. We try to finish it this week," he stated.