This Week, Sheet Pile Elevation on Jalan Asri 1 Completed

The 50-centimeter-high sheet pile elevation on Jalan Pelepah Asri 1, Janur Asri Housing Complex, RW 12 Kelapa Gading Barat Urban Village, Kelapa Gading, which has been underway since September 7 is targeted for completion this week.

This work involves eight personnel every day

Kelapa Gading Water Resources (SDA) Executing Unit Head, Citrin Indarwati said the sheet pile was elevated to 70 centimeters high.

"This work involves eight personnel every day," she expressed.

Collapsed Sheet Pile on Jalan Puri Kembangan Repaired

According to him, the sheet pile has a length of 86 meters and a width of 40 centimeters.

"Thus far, the work progress has touched 95 percent. We try to finish it this week," he stated.

Linked News
Popular News indeks
  1. Five Transjabodetabek Routes will Be Added to Tackle Traffic Congestion

    access_time09-05-2025 remove_red_eye670 personDessy Suciati
  2. Tanah Abang SDA Taskforce Normalizes Channels in Two Locations

    access_time12-05-2025 remove_red_eye459 personFolmer
  3. Community Work Held to Clean Environment in Petamburan

    access_time11-05-2025 remove_red_eye355 personFolmer
  4. Baduy Tribe Meets Pramono-Rano, Leaves Message of Protecting Nature

    access_time09-05-2025 remove_red_eye298 personDessy Suciati
  5. Reviewing Mookervart IPA, Pramono Wants to Improve Clean Water Services

    access_time09-05-2025 remove_red_eye292 personDessy Suciati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik