Peninggian Turap Saluran Jalan Asri 1 Rampung Pekan ini

This Week, Sheet Pile Elevation on Jalan Asri 1 Completed

The 50-centimeter-high sheet pile elevation on Jalan Pelepah Asri 1, Janur Asri Housing Complex, RW 12 Kelapa Gading Barat Urban Village, Kelapa Gading, which has been underway since September 7 is targeted for completion this week.

This work involves eight personnel every day

Kelapa Gading Water Resources (SDA) Executing Unit Head, Citrin Indarwati said the sheet pile was elevated to 70 centimeters high.

"This work involves eight personnel every day," she expressed.

Collapsed Sheet Pile on Jalan Puri Kembangan Repaired

According to him, the sheet pile has a length of 86 meters and a width of 40 centimeters.

"Thus far, the work progress has touched 95 percent. We try to finish it this week," he stated.

Linked News
Popular News indeks
  1. Cilandak Drainage Upgraded to Mitigate Flooding

    access_time27-01-2026 remove_red_eye868 personTiyo Surya Sakti
  2. TransJabodetabek Expansion, a Strategic Step to Increase Public Transportation Use

    access_time26-01-2026 remove_red_eye424 personFakhrizal Fakhri
  3. Jakarta Prepares OMC and 200 Excavators to Prevent Flood

    access_time26-01-2026 remove_red_eye371 personDessy Suciati
  4. Jakarta Showers to Make Way for Partly Cloudy Skies

    access_time30-01-2026 remove_red_eye358 personDessy Suciati
  5. Several Microtrans Routes Diverted

    access_time31-01-2026 remove_red_eye355 personAldi Geri Lumban Tobing
close