You don't have javascript enabled. Good luck with that.
Pencarian
Tanggul Pemecah Gelombang Sisi Utara Pulau Kelapa Diperbaiki

Collapsed Breakwater on Kelapa Island Repaired

The Seribu Islands Water Resources (SDA) Sub-agency is seen repairing the collapsed breakwater after being hit by high tide on the north side of RT 01/02, Kelapa Island, North Seribu Islands.

The work progress has touched 15 meters

Seribu Islands SDA Sub-agency Head, Hendri said the breakwater repair was carried out by reassembling the collapsed hollow cubes using nylon rope.

"These massive cubes have been falling since last October. We put them back together and tied them with slings, thus they are strong enough to withstand sea waves," he expressed, Thursday (11/9).

Breakwater on North Side of Panggang Island Being Repaired

He explained the cube installation involved six personnel equipped with one unit of heavy equipment. The breakwater along 127 meters will be completed in the forthcoming December 2023.

"The work progress has touched 15 meters. Hopefully, it can protect the island from abrasion," he stated.

Linked News
Popular News indeks
  1. Transjakarta Brings Lunar New Year Festivities to Public Transport

    access_time16-02-2026 remove_red_eye972 personAldi Geri Lumban Tobing
  2. Free Transit Card Applications Skyrocket 143%, Passing 76k Mark

    access_time20-02-2026 remove_red_eye933 personAldi Geri Lumban Tobing
  3. Jakarta Govt-City Council Step Up Coordination to Address Key Urban Challenges

    access_time22-02-2026 remove_red_eye827 personFakhrizal Fakhri
  4. Public Works Agency Gets Transjakarta Corridor 13 Back in Tip-Top Shape

    access_time17-02-2026 remove_red_eye710 personAldi Geri Lumban Tobing
  5. Chinese New Year Holiday, Ancol Flocked by Visitors

    access_time16-02-2026 remove_red_eye607 personAnita Karyati