You don't have javascript enabled. Good luck with that.
Pencarian
Tanggul Pemecah Gelombang Sisi Utara Pulau Kelapa Diperbaiki

Collapsed Breakwater on Kelapa Island Repaired

The Seribu Islands Water Resources (SDA) Sub-agency is seen repairing the collapsed breakwater after being hit by high tide on the north side of RT 01/02, Kelapa Island, North Seribu Islands.

The work progress has touched 15 meters

Seribu Islands SDA Sub-agency Head, Hendri said the breakwater repair was carried out by reassembling the collapsed hollow cubes using nylon rope.

"These massive cubes have been falling since last October. We put them back together and tied them with slings, thus they are strong enough to withstand sea waves," he expressed, Thursday (11/9).

Breakwater on North Side of Panggang Island Being Repaired

He explained the cube installation involved six personnel equipped with one unit of heavy equipment. The breakwater along 127 meters will be completed in the forthcoming December 2023.

"The work progress has touched 15 meters. Hopefully, it can protect the island from abrasion," he stated.

Linked News
Popular News indeks
  1. Pramono Pushes to Complete Long-Delayed Pluit JLNT by March 2027

    access_time20-11-2026 remove_red_eye697 personDessy Suciati
  2. JAF 2026 Highlights Maritime Heritage and Coastal Architecture

    access_time21-11-2026 remove_red_eye682 personAnita Karyati
  3. Hosted in Sydney, Pramono Discusses Opening Australian Campuses in Jakarta

    access_time25-11-2026 remove_red_eye665 personDessy Suciati
  4. Jakarta Strengthens ASEAN Cooperation on Climate, Transport, and Youth

    access_time20-11-2026 remove_red_eye638 personFolmer
  5. BORJU Markets 200 Local Products

    access_time20-11-2026 remove_red_eye607 personAnita Karyati