 Pembangunan Rumah Pompa Patra Capai 95 Persen

Patra Pump House Construction Reaches 95 Percent

The flood handling infrastructure keeps provided in West Jakarta. Now the West Jakarta Water Resources Sub-agency is completing the construction of Patra Pump House on Jalan Patra, RT 08/02, Duri Kepa Urban Village, Kebon Jeruk Sub-district.

operating the pump house in the middle of February 2024

Sub-agency Head, Purwanti, said the construction was started in October 2023 and completed in December 2023. In fact, the additional 50 working days are given since the bottom of stilling pool is sloping.

"We're speeding up the work. Now it reaches 95 percent or finishing stage," Purwanti said, Tuesday (1/23).

Heru Monitors Pump House Construction on Jalan Kemang Raya

Purwanti added that the finishing stages include plastering walls, installing floors and windows. Next is the installation of two pump machines with each pump capacity of 500 liters per second.

"Our target is operating the pump house in the middle of February 2024 to minimize inundation in the area," Purwanti added.

Suratmi (43), one of local residents, admitted Jalan Patra is often inundated during heavy rain.

"It is hoped the newly constructed pump house will minimize inundation here," she admitted.

Linked News
Popular News indeks
  1. Commission E Enlists Religious Leaders to Fight Drugs and Violence

    access_time24-07-2026 remove_red_eye1208 personFakhrizal Fakhri
  2. Jakarta Supports Social Media Restrictions for Children

    access_time20-07-2026 remove_red_eye1189 personFakhrizal Fakhri
  3. Fire at Spark Sport Academy Pondok Bambu Successfully Extinguished

    access_time20-07-2026 remove_red_eye1009 personNurito
  4. The 2026 SEA V Cup Officially Begins

    access_time23-07-2026 remove_red_eye932 personAldi Geri Lumban Tobing
  5. Pramono Praises Baznas and Private Sector Synergy at Home Renovation

    access_time21-07-2026 remove_red_eye760 personDessy Suciati