Cegah Genangan, Kelurahan Cibubur Bangun 10 Sumur Resapan
....
photo Nurito - Beritajakarta.id

PPSU Personnel of Cibubur Construct 10 Reservoir Wells

As many as eight PPSU personnel of Cibubur Urban Village, Ciracas, East Jakarta, construct 10 reservoir wells in order to minimize inundation during rainy season.

Wells' depth is 20 meter

Acting Cibubur Urban Village Head, Ronny Abdullah, said the construction is based on East Jakarta Mayor's instruction to construct 40 reservoir wells at prone to inundation areas this year.

Construction of Mandor Hasan Reservoir Begins

"As for the early stage, we construct the first 10 wells," he said, Friday (5/31).

Cibubur Urban Village Economy and Development Section Head, Heru Kristianto, stated those 10 reservoir wells are at urban village office's yard by four wells, Jalan Lapangan Tembak by four wells, and Jalan Jambore by two wells.

"Wells' depth is 20 meter. It takes four days to construct one well," he stated.

Linked News
Popular News indeks
  1. Five Transjabodetabek Routes will Be Added to Tackle Traffic Congestion

    access_time09-05-2025 remove_red_eye670 personDessy Suciati
  2. Tanah Abang SDA Taskforce Normalizes Channels in Two Locations

    access_time12-05-2025 remove_red_eye459 personFolmer
  3. Community Work Held to Clean Environment in Petamburan

    access_time11-05-2025 remove_red_eye355 personFolmer
  4. Baduy Tribe Meets Pramono-Rano, Leaves Message of Protecting Nature

    access_time09-05-2025 remove_red_eye298 personDessy Suciati
  5. Reviewing Mookervart IPA, Pramono Wants to Improve Clean Water Services

    access_time09-05-2025 remove_red_eye292 personDessy Suciati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik