Perbaikan Turap Waduk Bojong Indah Capai 70 Persen

Bojong Indah Reservoir Plastering Reaches 70 Percent

The improvement of Bojong Indah Reservoir plaster on Jalan Belimbing Raya, RT 05/11, Rawa Buaya Urban Village, Cengkareng Sub-district, West Jakarta, is being rushed.

We are targeting two months

West Jakarta Water Resource Sub-agency Head, Purwanti, said repairs were carried out after the retaining wall collapsed then causing damage. Repairs began in mid-February 2024, spanning 48 meters.

"Now the repair has reached 70 percent," Purwanti said, Thursday (9/5).

E. Jakarta Mayor: Pekayon Emaung Must Have Drainage Tank

Purwanti added that the project involves 15 personnel of West Jakarta Water Resource Sub-agency with one excavator.

"Currently, personnel are digging the ground and installing dolken wood. Next, river stones will be installed and plastered using a mixture of sand and cement. We are targeting two months for this repair to be completed," Purwanti stated.

Linked News
Popular News indeks
  1. Central Jakarta Administration Acts Swiftly to Handle Kebon Kosong Fire

    access_time02-06-2026 remove_red_eye1451 personFolmer
  2. Public Urged to Use Public Transit for GBK Events to Avoid Heavy Traffic

    access_time05-06-2026 remove_red_eye1144 personAldi Geri Lumban Tobing
  3. Central Jakarta Government Responds Quickly to Fire Victims in Tanah Tinggi

    access_time04-06-2026 remove_red_eye980 personFolmer
  4. Jakarta Waives Motor Vehicle Tax Fines and Title Transfer Fees

    access_time01-06-2026 remove_red_eye884 personAldi Geri Lumban Tobing
  5. Traffic Measures Prepared to Ease Congestion Around GBK This Weekend

    access_time04-06-2026 remove_red_eye833 personAldi Geri Lumban Tobing