Pembangunan Tiga Tanggul di Kepulauan Seribu Ditarget Kelar Desember

Breakwater Construction on Three Islands to Complete December

The Seribu Island Water Resource Sub-agency targets to complete the construction of breakwater on three residential islands on December 8, 2024. The construction has been starting since June 12, 2024.

also includes building roads on embankments

Seribu Island Water Resource Sub-agency Head, Mustajab, said the construction is part of Regional Strategic Program (KSD) to protect mainland from sea wave.

Gabions Installation Progress on Karya Island Reaches 70 Percent

"The function of this embankment is as an abrasion retaining wall as well as a boundary between the mainland area and the coastal area and as an outermost boundary ring road," he said, Wednesday (9/11).

Mustajab explained the construction of breakwater on Tidung Island and Lancang Island, Seribu Selatan Sub-district, and on Panggang Island, Seribu Utara Sub-district spent Rp 56.12 billion.

"The budget allocation also includes building roads on embankments," he explained.

According to him, the embankment constructions almost reach 50 percent.

"The constructions are targeted to complete in 180 working days," he added.

Mustajab detailed, for the length of the embankment on Tidung Island, it is made 450 meters long with a width of 3 meters. Then, on Lancang Island there are two parts, the first part is 240 meters long with a width of three meters and the second part is 127 meters long with a top width of 1.2 meters and a bottom area of ​​4.8 meters.

"On Panggang Island, the planned length of the embankment will reach 152 meters, with a top width of 0.4 meters and a bottom width of 8.6 meters," he detailed.

He hopes that the construction of breakwaters on the three residential islands can be completed simultaneously this year, even though it is often hampered by high waves or high tides.

Meanwhile, RW 02 Head, Tidung Island Urban Village, Wawan, appreciated and thanked the Seribu Island Water Resource Sub-agency for constructing the breakwater.

"Monitoring and supervising will be conducted together with the residents. Hopefully the construction of this embankment can be completed according to target and provide optimal benefits," he hoped.

Linked News
Popular News indeks
  1. Pramono Affirms Commitment to Enhancing Regional Financial Management Quality

    access_time02-04-2026 remove_red_eye838 personTiyo Surya Sakti
  2. Posyandu-Posbindu Services Reach 1,600 Seniors and Toddlers in Utan Panjang

    access_time07-04-2026 remove_red_eye784 personFolmer
  3. Kampung Rambutan Terminal Sees Increase in Intercity Bus Passengers

    access_time03-04-2026 remove_red_eye783 personNurito
  4. Banners Prohibiting Illegal Parking Levies Installed at Blok M Square

    access_time02-04-2026 remove_red_eye678 personTiyo Surya Sakti
  5. West Jakarta BPN Holds Mobile Land Service in Kembangan

    access_time06-04-2026 remove_red_eye628 personBudhi Firmansyah Surapati