Water Channel Normalization in UKU to Complete Today
access_time September 11 2024 05:25 PM remove_red_eye 254
Reported by Nurito | Translated by Rizky Mawardi
Reported by Nurito | Translated by Rizky Mawardi
The water channel normalization on Jalan Srikaya RT 05/05, Utan Kayu Utara Urban Village (UKU), Matraman, East Jakarta, Wednesday (9/11) to complete today. The work was started on August 29.
We normalized water channel along 40 meters
Matraman Sub-district's Water Resource Taskforce Coordinator, Saeful, said the normalization of the 40-meter long water channel was carried out by tidying up the retaining wall and installing concrete cover on the top to make it more comfortable for vehicles.
Progress of Sidewalk Arrangement in Pondok Kelapa Reaches 40 Percent"We normalized water channel along 40 meters. The work is complete today," he said.
He added that the work involved eight personnel since August 29.
"Personnel only installing plaster on the left and right sides of the concrete cover to make it stronger," he stated.