Proyek Jalan Inspeksi Kali Mookervart Terkendala
.
photo Ilustrasi - Beritajakarta.id

Mookevart River Project Hampered by Land Acquisition

The road inspection project of Mookevart river in Kalideres, West Jakarta is still hampered by land acquisition.  As recorded, there are still 14 landowners claimed have not received compensation from the city administration.

While other land payment has been processed by Water Management Sub-Department

Land Acquisition in Bidara Cina Targeted to Be Completed This Year

Kalideres Sub-District Head, Yunus Burhan mentioned, his side still appraise the land and building value that will be paid to residents.

“While other land payment has been processed by Water Management Sub-Department,” he uttered, Wednesday (5/13).

The Executor Coordinator of City Dam and River Normalization, Heriyanto added, the length of the project is 8 kilometers, that had been completed by 2 kilometers. The project targeted must be done by this year.

Linked News
Popular News indeks
  1. Jakarta Vice Governor Rano Wishes a Happy Eid al-Fitr 1446 Hijri

    access_time31-03-2025 remove_red_eye591 personFolmer
  2. Monas Prepares to Greet Visitors This Eid Holiday

    access_time30-03-2025 remove_red_eye579 personDessy Suciati
  3. Foul Smell Around JGC Clarified Not Coming from Rorotan RDF

    access_time28-03-2025 remove_red_eye431 personAldi Geri Lumban Tobing
  4. Residents Hope Another Free Homecoming Program Held Next Year

    access_time27-03-2025 remove_red_eye316 personDessy Suciati
  5. Odd-Even Policy in Jakarta Put on Hold for Eid Break

    access_time28-03-2025 remove_red_eye283 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik