Utan Kayu River Retaining Wall Repair to be Completed Early December
access_time November 12 2024 11:59 PM remove_red_eye 250
Reported by Nurito | Translated by Rizky Mawardi
Reported by Nurito | Translated by Rizky Mawardi
The repair of Utan Kayu River retaining wall in Matraman, East Jakarta run by third party since November 3 is targeted to complete in early December.
The broken part is along 45 meter
East Jakarta Water Resource Sub-agency's Maintenance Section Head, Puryanto Palebangan, explained the 88-meter long retaining wall, which is still under repair by a third party, was broken due to being eroded by the overflow of the Utan Kayu River during heavy rain.
Anwar: Repair of Utan Kayu River Sheet Pile must Be Accelerated"The broken part is along 45 meter," he said, Tuesday (11/12).
Project Implementer, Harlen Sitorus, said the repair is now entering the finishing stage.
"Personnel are working on sloop casting and plastering of the retaining wall. It is targeted to complete in early December.