 Perbaikan Turap Longsor di Matraman Capai 80 Persen
.
photo Nurito - Beritajakarta.id

Utan Kayu River Retaining Wall Repair to be Completed Early December

The repair of Utan Kayu River retaining wall in Matraman, East Jakarta run by third party since November 3 is targeted to complete in early December.

The broken part is along 45 meter

East Jakarta Water Resource Sub-agency's Maintenance Section Head, Puryanto Palebangan, explained the 88-meter long retaining wall, which is still under repair by a third party, was broken due to being eroded by the overflow of the Utan Kayu River during heavy rain.

Anwar: Repair of Utan Kayu River Sheet Pile must Be Accelerated

"The broken part is along 45 meter," he said, Tuesday (11/12).

Project Implementer, Harlen Sitorus, said the repair is now entering the finishing stage.

"Personnel are working on sloop casting and plastering of the retaining wall. It is targeted to complete in early December.

Linked News
Popular News indeks
  1. Tanah Abang SDA Taskforce Normalizes Channels in Two Locations

    access_time12-05-2025 remove_red_eye466 personFolmer
  2. Community Work Held to Clean Environment in Petamburan

    access_time11-05-2025 remove_red_eye361 personFolmer
  3. Food Station Signs Farming Contracts in Rorotan

    access_time12-05-2025 remove_red_eye308 personAldi Geri Lumban Tobing
  4. Commission D Supports Construction of Rorotan Rusunawa

    access_time10-05-2025 remove_red_eye263 personFakhrizal Fakhri
  5. Pramono Focuses on Increasing Equal Access to Education

    access_time15-05-2025 remove_red_eye262 personDessy Suciati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik