You don't have javascript enabled. Good luck with that.
Pencarian
 Perbaikan Turap Longsor di Matraman Capai 80 Persen
.
photo Nurito - Beritajakarta.id

Utan Kayu River Retaining Wall Repair to be Completed Early December

The repair of Utan Kayu River retaining wall in Matraman, East Jakarta run by third party since November 3 is targeted to complete in early December.

The broken part is along 45 meter

East Jakarta Water Resource Sub-agency's Maintenance Section Head, Puryanto Palebangan, explained the 88-meter long retaining wall, which is still under repair by a third party, was broken due to being eroded by the overflow of the Utan Kayu River during heavy rain.

Anwar: Repair of Utan Kayu River Sheet Pile must Be Accelerated

"The broken part is along 45 meter," he said, Tuesday (11/12).

Project Implementer, Harlen Sitorus, said the repair is now entering the finishing stage.

"Personnel are working on sloop casting and plastering of the retaining wall. It is targeted to complete in early December.

Linked News
Popular News indeks
  1. Commission E Urges Residents to Increase Role in Preventing DHF

    access_time19-12-2024 remove_red_eye1198 personDessy Suciati
  2. Transjakarta Adjusting Service as Simpang Pramuka and Rawamangun Bus Stops Closed

    access_time18-12-2024 remove_red_eye1041 personAldi Geri Lumban Tobing
  3. Transjakarta, Telkomsel to Improve Service for Customers

    access_time19-12-2024 remove_red_eye895 personAldi Geri Lumban Tobing
  4. Acting Governor Monitors Food Stock at Kramat Jati and Cipinang Markets

    access_time19-12-2024 remove_red_eye720 personFolmer
  5. Transjakarta Extends Service Hours to Four Terminals during Christmas

    access_time20-12-2024 remove_red_eye558 personAldi Geri Lumban Tobing