 Perbaikan Turap Longsor di Matraman Capai 80 Persen

Utan Kayu River Retaining Wall Repair to be Completed Early December

The repair of Utan Kayu River retaining wall in Matraman, East Jakarta run by third party since November 3 is targeted to complete in early December.

The broken part is along 45 meter

East Jakarta Water Resource Sub-agency's Maintenance Section Head, Puryanto Palebangan, explained the 88-meter long retaining wall, which is still under repair by a third party, was broken due to being eroded by the overflow of the Utan Kayu River during heavy rain.

Anwar: Repair of Utan Kayu River Sheet Pile must Be Accelerated

"The broken part is along 45 meter," he said, Tuesday (11/12).

Project Implementer, Harlen Sitorus, said the repair is now entering the finishing stage.

"Personnel are working on sloop casting and plastering of the retaining wall. It is targeted to complete in early December.

Linked News
Popular News indeks
  1. Suckermouth Catfish Control for Environmental Preservation

    access_time18-04-2026 remove_red_eye797 personFakhrizal Fakhri
  2. Jakarta to Hold Citywide Lights-Out Initiative

    access_time24-04-2026 remove_red_eye731 personAldi Geri Lumban Tobing
  3. Suckerfish Handling in South Jakarta is Run in Accordance with MUI Recommendations

    access_time21-04-2026 remove_red_eye636 personTiyo Surya Sakti
  4. Rano Leads Parking Arrangement on Jalan R.A. Kartini, Lebak Bulus

    access_time24-04-2026 remove_red_eye409 personBudhi Firmansyah Surapati
  5. Jakarta Newcomers Mostly in Productive Age

    access_time22-04-2026 remove_red_eye394 personAldi Geri Lumban Tobing