Traffic on Jalan Pemuda and Pramuka Underpass Diverted
Reported by Aldi Geri Lumban Tobing | Translated by Rizky Mawardi
Jakarta Transportation is about to rearrange traffic on Jalan Pemuda and Pramuka Underpass related with LRT Jakarta Phase 1B Velodrome-Manggarai Zone 1 construction.
based on the work stages
"The traffic rearrangement is run based on the work stages starting on December 11, 2024 up to January 19, 2025," said Syafrin Liputo, Jakarta Transportation Agency Head, Friday (12/13).
Here are the following work stages with the traffic rearrangement;
Traffic Arrangement Applied on Jalan Tambaka. P103B-101B Work (Pramuka underpass ramp East side);
- Borepile and column work, there will be road reduction/narrowing during the work;
- The underpass planter box and slow-fast lane median will be dismantled to add road width occupied by the project;
- The work runs on December 11, 2024 up to January 19, 2025;
b. Erection girder P35-P45 on Jalan Pemuda;
- There are eleven column spans, where each column consists of two spans;
- The work runs on December 11-24, 2024 at 10 PM to 4 AM;
- Traffic diversion will applied during the work; traffic on Jalan Pemuda South side, then traffic from East and West is diverted on Jalan Sunan Giri-Jalan Rawamangun Muka-Jalan Jenderal Ahmad Yani-and so on, then Transjakarta to use Jalan Balap Sepeda and on son.
- Traffic from West heading to East can use Jalan Pemuda North side;
- The diversion will be adjusted if there are Christmas and New Year events
"Road users are appealed to avoid those roads to use the determined direction, obey traffic signs, follow field officers instruction and prioritize road safety," he stated.