Dishub Rekayasa Lalu Lintas Jalan Pemuda dan Underpass Pramuka

Traffic on Jalan Pemuda and Pramuka Underpass Diverted

Jakarta Transportation is about to rearrange traffic on Jalan Pemuda and Pramuka Underpass related with LRT Jakarta Phase 1B Velodrome-Manggarai Zone 1 construction.

based on the work stages

"The traffic rearrangement is run based on the work stages starting on December 11, 2024 up to January 19, 2025," said Syafrin Liputo, Jakarta Transportation Agency Head, Friday (12/13).

Here are the following work stages with the traffic rearrangement;

Traffic Arrangement Applied on Jalan Tambak

a. P103B-101B Work (Pramuka underpass ramp East side);

- Borepile and column work, there will be road reduction/narrowing during the work;

- The underpass planter box and slow-fast lane median will be dismantled to add road width occupied by the project;

- The work runs on December 11, 2024 up to January 19, 2025;

b. Erection girder P35-P45 on Jalan Pemuda;

- There are eleven column spans, where each column consists of two spans;

- The work runs on December 11-24, 2024 at 10 PM to 4 AM;

- Traffic diversion will applied during the work; traffic on Jalan Pemuda South side, then traffic from East and West is diverted on Jalan Sunan Giri-Jalan Rawamangun Muka-Jalan Jenderal Ahmad Yani-and so on, then Transjakarta to use Jalan Balap Sepeda and on son.

- Traffic from West heading to East can use Jalan Pemuda North side;

- The diversion will be adjusted if there are Christmas and New Year events

"Road users are appealed to avoid those roads to use the determined direction, obey traffic signs, follow field officers instruction and prioritize road safety," he stated.

Linked News
Popular News indeks
  1. Jakarta Taps MSMEs and Creative Economy to Secure Global Top 50 Spot

    access_time11-07-2026 remove_red_eye1692 personAldi Geri Lumban Tobing
  2. Ciliwung River Normalization Accelerated, Pramono Ensures Land Acquisition Without Intermediaries

    access_time10-07-2026 remove_red_eye1476 personDessy Suciati
  3. Blocked Drain on Jalan Palmerah Utara is Being Repaired

    access_time10-07-2026 remove_red_eye1333 personFolmer
  4. Pramono will Take Firm Action Against Individuals Involved in Extortion

    access_time13-07-2026 remove_red_eye1116 personDessy Suciati
  5. The Pegangsaan Dua-Manggarai LRT Project Reaches 95 Percent Completion

    access_time14-07-2026 remove_red_eye806 personDessy Suciati