Traffic Engineering to Be Applied on East Side of Jalan Raya Bogor
Reported by Aldi Geri Lumban Tobing | Translated by Rizky Mawardi
Jakarta Transportation Agency is about to apply traffic engineering on east side of Jalan Raya Bogor, East Jakarta as the pipe installation of Drinking Water Supply System to be run on the location.
road lane will be reduced
Jakarta Transportation Agency Head, Syafrin Liputo said there will be five digging areas to be run in stages on Jalan Raya Bogor after Pasar Rebo Intersection.
"The road lane will be reduced during the work. But a deck plate to be installed situationally during rush hour," he said, Sunday (1/12).
PAM Jaya Studies Plans to Increase Water TariffsTraffic engineering to be run are listed below;
a. Stage 1; Connecting pit 4 to pit 5 from January 18 to January 31, 2025.
b. Stage 2; Connecting pit 4 to pit 3 on February 1-14, 2025, after pit 5 is completed.
c. Stage 3; Connecting pit 2 to pit 1 on February 15-28, 2025, after pit 4 and pit 3 are completed.
d. Stage 4; Connecting pit 2 to pit 3 on March 1-14, 2025, after pit 1 is completed.
e. Excavation repairing and finishing on March 15 to April 11, 2025.
"We appeal road users to avoid that road and adjust the traffic arrangement. Please obey traffic signs, our personnel instruction, and prioritize road safety," he stated.