End of May, Channel Dredging on Jalan Ahmad Yani Completed

The connection channel on Jalan Jenderal A Yani, RW 07, Cempaka Putih Timur, Cempaka Putih is being expedited. This has been underway since last week and is targeted to be completed by the end of May 2025.

The work progress has touched around 45 percent or along 120 meters

Cempaka Putih Sub-district Water Resources (SDA) Executing Unit Head, Sahudi said the dredging along 264 meters is carried out to follow up on residents' complaints via Jakarta Kini (JAKI) application.

"14 personnel are involved in this work," he expressed, Tuesday (5/6).

200 S. Jakarta SDA Personnel Mobilized to Dredge Cabang Tengah River

According to him, the channel, which has a height and width of 160 centimeters, has sediment accumulation of 20 centimeters. If it is not dredged, it will cause flooding when it rains.

"The work progress has touched around 45 percent or along 120 meters," he stated.

Linked News
Popular News indeks
  1. Jakarta Calls on Residents to Save Energy with 60-Minute Lights-Off Action

    access_time19-09-2026 remove_red_eye425 personAldi Geri Lumban Tobing
  2. Indonesia-Singapore Match: 80 Dishub Personnel Deployed to Manage Traffic Around GBK

    access_time25-09-2026 remove_red_eye414 personAldi Geri Lumban Tobing
  3. Jakarta International Stadium Sets Up Transit Schemes for The Weeknd Concert

    access_time24-09-2026 remove_red_eye404 personAldi Geri Lumban Tobing
  4. South Jakarta BPBD Distributes 44,000 Liters of Clean Water

    access_time19-09-2026 remove_red_eye362 personTiyo Surya Sakti
  5. Jakarta Inspectorate Partners with KPK to Foster Early Anti-Corruption Culture

    access_time20-09-2026 remove_red_eye308 personFolmer