The connection channel on Jalan Jenderal A Yani, RW 07, Cempaka Putih Timur, Cempaka Putih is being expedited. This has been underway since last week and is targeted to be completed by the end of May 2025.

The work progress has touched around 45 percent or along 120 meters

Cempaka Putih Sub-district Water Resources (SDA) Executing Unit Head, Sahudi said the dredging along 264 meters is carried out to follow up on residents' complaints via Jakarta Kini (JAKI) application.

"14 personnel are involved in this work," he expressed, Tuesday (5/6).

200 S. Jakarta SDA Personnel Mobilized to Dredge Cabang Tengah River

According to him, the channel, which has a height and width of 160 centimeters, has sediment accumulation of 20 centimeters. If it is not dredged, it will cause flooding when it rains.

"The work progress has touched around 45 percent or along 120 meters," he stated.

Linked News
Popular News indeks
  1. Pramono Pushes to Complete Long-Delayed Pluit JLNT by March 2027

    access_time20-11-2026 remove_red_eye697 personDessy Suciati
  2. JAF 2026 Highlights Maritime Heritage and Coastal Architecture

    access_time21-11-2026 remove_red_eye683 personAnita Karyati
  3. Hosted in Sydney, Pramono Discusses Opening Australian Campuses in Jakarta

    access_time25-11-2026 remove_red_eye669 personDessy Suciati
  4. Jakarta Strengthens ASEAN Cooperation on Climate, Transport, and Youth

    access_time20-11-2026 remove_red_eye638 personFolmer
  5. BORJU Markets 200 Local Products

    access_time20-11-2026 remove_red_eye607 personAnita Karyati