End of May, Channel Dredging on Jalan Ahmad Yani Completed

The connection channel on Jalan Jenderal A Yani, RW 07, Cempaka Putih Timur, Cempaka Putih is being expedited. This has been underway since last week and is targeted to be completed by the end of May 2025.

The work progress has touched around 45 percent or along 120 meters

Cempaka Putih Sub-district Water Resources (SDA) Executing Unit Head, Sahudi said the dredging along 264 meters is carried out to follow up on residents' complaints via Jakarta Kini (JAKI) application.

"14 personnel are involved in this work," he expressed, Tuesday (5/6).

200 S. Jakarta SDA Personnel Mobilized to Dredge Cabang Tengah River

According to him, the channel, which has a height and width of 160 centimeters, has sediment accumulation of 20 centimeters. If it is not dredged, it will cause flooding when it rains.

"The work progress has touched around 45 percent or along 120 meters," he stated.

Linked News
Popular News indeks
  1. Transjakarta Commits to Accelerating Modal Integration and Fleet Electrification

    access_time31-08-2026 remove_red_eye600 personAldi Geri Lumban Tobing
  2. JITEX 2026: Fostering a Global Trade and Investment Ecosystem

    access_time01-09-2026 remove_red_eye562 personAldi Geri Lumban Tobing
  3. Pramono Confirms Permanent Bridge to Be Built in Tegal Alur

    access_time29-08-2026 remove_red_eye460 personDessy Suciati
  4. Jakarta Fine Arts and Ceramics Museum Hosts Malangan Exhibition

    access_time29-08-2026 remove_red_eye457 personFakhrizal Fakhri
  5. Pramono Emphasizes Importance of Creative Spaces for Children

    access_time03-09-2026 remove_red_eye434 personDessy Suciati