Giri Kencana Reservoir on Jalan Giri Kencana Revitalized

Giri Kencana Reservoir located on Jalan Giri Kencana, RW 03 and 06, Cilangkap Urban Gillage, Cipayung Sub-district, East Jakarta has begun to be revitalized.

Currently, the progress of the work has only reached about 5.6 percent

East Jakarta Water Resources (SDA) Sub-agency's Maintenance Section Head, Tengku Saugi Zikri said, the revitalization of Giri Kencana Reservoir began in early June.

"Currently, the progress of the work has only reached about 5.6 percent," he expressed, Thursday (7/3).

City Prepares Mosque Sound System Revitalization Program in 2026

He explained the project included land dredging in the wet cross-section, constructing retaining walls using gabions or bronjong, and their various components.

"Third party will execute this project at a cost by Rp 56.1 billion from City Budget (APBD). It is targeted to be completed by December 15," he explained.

There would be dredging, increasing the current depth from three meters to an additional two meters. As a result, the reservoir deep would have 5 meters.

"We project that this reservoir can prevent floods that usually occur in the RW 02, 03, 04, and 06 areas of Cilangkap Urban Village," he explained.

He added, it would also have various facilities such as an information centre, meeting and storage rooms, toilets, a prayer hall, an sports zone, gazebos, an amphitheater, a playground and children's play facilities, as well as a bridge.

Giri Kencana Reservoir Revitalization Project Vice Manager, Bernard Saragih explained, the revitalization work at the 4.5-hectare reservoir was being accelerated to be completed following the set target.

"Currently, we're conducting land excavation or dredging and attaching retaining walls using stone gabions surrounding the reservoir area," he explained.

He added gabions were installed using a six-trap model to ensure stability and prevent landslides of the reservoir. The gabions currently installed amount to approximately 1,700 cubic meters, or along 150 meters out of a total of 800 meters.

He added, the reservoir would also have a jogging track area and a 900-meter-long running track with 2.5 meters wide.

"Greening will also be done with plants," he added.

Linked News
Popular News indeks
  1. Pramono Flags Off 10,000 Runners at Soekarno Run 2026

    access_time15-02-2026 remove_red_eye1058 personFolmer
  2. Jakarta Unveils Indonesia’s First SDGs Corner at Maritime Museum

    access_time15-02-2026 remove_red_eye994 personNurito
  3. Transjakarta Brings Lunar New Year Festivities to Public Transport

    access_time16-02-2026 remove_red_eye966 personAldi Geri Lumban Tobing
  4. Free Transit Card Applications Skyrocket 143%, Passing 76k Mark

    access_time20-02-2026 remove_red_eye926 personAldi Geri Lumban Tobing
  5. Public Works Agency Gets Transjakarta Corridor 13 Back in Tip-Top Shape

    access_time17-02-2026 remove_red_eye706 personAldi Geri Lumban Tobing