 Progres Pembangunan LRT Velodrome-Manggarai

Velodrome-Manggarai LRT Construction Reaches 69.88 Percent

The construction of the Jakarta LRT Phase 1B Velodrome-Manggarai along 6.4 kilometer continues to show positive progress.

provide solutions to traffic congestion

PT Jakarta Propertindo (Perseroda) or Jakpro recorded that the project's progress reached 69.88 percent by the second week of September 2025. This marks a significant step forward in providing a modern, integrated, and environmentally friendly mode of transportation in Jakarta.

Significant progress is currently visible in Zone 1, namely Jalan Pemuda Rawamangun and Jalan Pramuka Raya, which have now reached 69.06 percent completion. The work currently underway includes the installation of elevated girders, the casting of slab decks, and the installation of parapet walls.

Pramono Calls on Public to Take Advantage of Rp1 Public Transport Fare

Construction of a special span is underway at a crucial point, the Wiyoto Wiyono Toll Road crossing. This highly complex project is proceeding on schedule while maintaining high safety and security standards.

Jakarta LRT Project Director Ramdani Akbar said that security, safety, and punctuality are commitments made by Jakpro and the implementing contractor.

"We ensure that every construction stage follows strict safety and security procedures. With this positive progress, we are optimistic that the project will soon provide solutions to traffic congestion and benefit the community," he said, Wednesday (9/17).

According to him, this strategic project is designed to expand the Jakarta LRT service which previously operated from Kelapa Gading to Velodrome, so that the phase 1A and 1B lines will have a total track length of 12.2 km with a travel time of 28 minutes.

"It is expected to be a solution to traffic congestion, strengthen intermodal connectivity, and support the development of public transportation in Jakarta," he added

As for information, in the Zone 2 area, namely Matraman, Jalan Tambak, and Manggarai, it has now reached 55.48 percent, with the achievement in the Matraman Flyover area where foundation work is currently being carried out and on Jalan Tambak trackworks will soon be carried out.

Meanwhile, in preparation for the Double Double Track (DDT) crossing in Manggarai, pile cap and pier work is currently underway, and on the Jalan Sultan Agung area, concrete girders are being installed for the elevated track during the window time.

"Jakarta LRT Phase 1B not only increases public transportation capacity, but also accelerates Jakarta's transformation into a sustainable and competitive global city," he stated.

Linked News
Popular News indeks
  1. Governor Attends Melasti Ceremony at Segara Temple

    access_time15-03-2026 remove_red_eye558 personBudhi Firmansyah Surapati
  2. East Jakarta Satpol PP Deployed to Ensure Safe Eid Travel Period

    access_time16-03-2026 remove_red_eye410 personNurito
  3. Pramono Inaugurates 26 Home Renovation Units

    access_time16-03-2026 remove_red_eye386 personDessy Suciati
  4. Travelers Departing from Lebak Bulus Terminal Starting to Increase

    access_time13-03-2026 remove_red_eye311 personTiyo Surya Sakti
  5. Jakarta Planetarium Rolls Out Varied Shows for Eid al-Fitr Holiday

    access_time11-03-2026 remove_red_eye305 personAldi Geri Lumban Tobing