Revitalization of Water Channel on Jalan Kramat Almost Complete

Eight personnel from the Ciracas Sub-district Water Resources Implementation Unit (SDA), East Jakarta, deployed to revitalize the water channels on Jalan Kramat, RT 10/10, Ciracas Urban Village. The progress has now reached 80 percent.

To be completed within 20 working days

Ciracas Sub-district SDA Executing Unit Head, Yulia Indah said, the revitalization of a 25-meter-long water channel was conducted by installing a U-ditch measuring 40x40x120 centimeters.

"This work started on September 15, 2025, and is scheduled to be completed within 20 working days," she expressed, Friday (10/3).

Water Channel on Jalan Dukuh Being Revitalized to Block Flooding

She explained, the previous channel only used four-inch pipes and had many damages that caused blockages.

"Hopefully, the revitalization of the water channels can optimally prevent flooding, especially during heavy rains," she explained.

The work received appreciation from RW 10 Chairman, Ciracas Urban Village, Sukimin.

"Despite the channel has not been fully completed, it is already functioning. In fact, during the heavy rain yesterday, water flowed directly through the new channel and the residents' houses are no longer flooding as before," he stated.

Linked News
Popular News indeks
  1. MRT Jakarta Integrates Ticket Payments with JakLingko from October 12

    access_time10-10-2026 remove_red_eye581 personAldi Geri Lumban Tobing
  2. New Kelapa Gading-Pulogadung Road to Ease Traffic and Improve Access

    access_time10-10-2026 remove_red_eye547 personAldi Geri Lumban Tobing
  3. Transjakarta Modifies Mikrotrans Routes JAK 48A, JAK 50, and JAK 79

    access_time12-10-2026 remove_red_eye514 personAldi Geri Lumban Tobing
  4. Way to Go, Kid! Transjakarta Surprises Young Local Commuter in East Jakarta

    access_time11-10-2026 remove_red_eye445 personAldi Geri Lumban Tobing
  5. Jakarta Sends Transport Personnel to Street Level to Clear Morning Rush-Hour Jams

    access_time11-10-2026 remove_red_eye348 personAldi Geri Lumban Tobing