Desember, Normalisasi Kali Ciliwung Ditargetkan Rampung

Ciliwung River Normalization Targeted to Finish This December

The normalization project for Ciliwung River in Kampung Pulo, Kampung Melayu Urban Village has reached 36 percent.

The road is two ways. It is hoped to finish in December

The project includes dredging, widening, installing sheetpile, providing jogging track, and inspection road along 1,950 meter. It is targeted to finish in December this year.

Agus Triwibowo, project manager, said the first stage of this project is dredging the river and continued by widening the river between 35 up to 50 meter.

129 Illegal Buildings Around Tugu Tani will Be Demolished

"Next are installing sheetpile and cropingphile, also jogging track as wide as three meter," he said, Monday (10/12).

Furthermore, road inspection will be constructed along the river bank by 7.2 meter of width starting from Kampung Melayu bridge up to Tongtek. Later on, the road will be used as alternative access from Tebet towards Matraman Raya.

"The road is two ways. It is hoped to finish in December," he disclosed.

Linked News
Popular News indeks
  1. Jakarta Claims Rp 2.27 T in Public Assets from Developer Obligations

    access_time06-08-2026 remove_red_eye645 personDessy Suciati
  2. New LapakMain Corner Creative Hub Inaugurated at Tunas Muda RPTRA, Kramat Pela

    access_time05-08-2026 remove_red_eye581 personTiyo Surya Sakti
  3. East Jakarta Red Cross Provides Aid to Utan Kayu Utara Fire Survivors

    access_time07-08-2026 remove_red_eye443 personNurito
  4. Thousand Islands Conducts Vehicle Emission Tests on Three Islands

    access_time07-08-2026 remove_red_eye402 personAnita Karyati
  5. Jakarta Remains Indonesia's Top Investment Destination

    access_time07-08-2026 remove_red_eye401 personAldi Geri Lumban Tobing