You don't have javascript enabled. Good luck with that.
Pencarian
Desember, Normalisasi Kali Ciliwung Ditargetkan Rampung

Ciliwung River Normalization Targeted to Finish This December

The normalization project for Ciliwung River in Kampung Pulo, Kampung Melayu Urban Village has reached 36 percent.

The road is two ways. It is hoped to finish in December

The project includes dredging, widening, installing sheetpile, providing jogging track, and inspection road along 1,950 meter. It is targeted to finish in December this year.

Agus Triwibowo, project manager, said the first stage of this project is dredging the river and continued by widening the river between 35 up to 50 meter.

129 Illegal Buildings Around Tugu Tani will Be Demolished

"Next are installing sheetpile and cropingphile, also jogging track as wide as three meter," he said, Monday (10/12).

Furthermore, road inspection will be constructed along the river bank by 7.2 meter of width starting from Kampung Melayu bridge up to Tongtek. Later on, the road will be used as alternative access from Tebet towards Matraman Raya.

"The road is two ways. It is hoped to finish in December," he disclosed.

Linked News
Popular News indeks
  1. JRF, Ye Concert Inject Rp 625 Billion into Jakarta's Economy

    access_time26-10-2026 remove_red_eye525 personDessy Suciati
  2. Transjakarta Adjusts Routes Amid Demonstrations

    access_time28-10-2026 remove_red_eye498 personAldi Geri Lumban Tobing
  3. Tourism Industry Workforce Capacity Continues to Be Improved

    access_time30-10-2026 remove_red_eye473 personAldi Geri Lumban Tobing
  4. Central Jakarta Helps 879 Residents Retrieve Withheld Diplomas

    access_time30-10-2026 remove_red_eye462 personFolmer
  5. Free Health Checks and TB Screening Held at RPTRA Tamplas Bambu

    access_time30-10-2026 remove_red_eye451 personNurito