Desember, Normalisasi Kali Ciliwung Ditargetkan Rampung

Ciliwung River Normalization Targeted to Finish This December

The normalization project for Ciliwung River in Kampung Pulo, Kampung Melayu Urban Village has reached 36 percent.

The road is two ways. It is hoped to finish in December

The project includes dredging, widening, installing sheetpile, providing jogging track, and inspection road along 1,950 meter. It is targeted to finish in December this year.

Agus Triwibowo, project manager, said the first stage of this project is dredging the river and continued by widening the river between 35 up to 50 meter.

129 Illegal Buildings Around Tugu Tani will Be Demolished

"Next are installing sheetpile and cropingphile, also jogging track as wide as three meter," he said, Monday (10/12).

Furthermore, road inspection will be constructed along the river bank by 7.2 meter of width starting from Kampung Melayu bridge up to Tongtek. Later on, the road will be used as alternative access from Tebet towards Matraman Raya.

"The road is two ways. It is hoped to finish in December," he disclosed.

Linked News
Popular News indeks
  1. Pramono Affirms Commitment to Enhancing Regional Financial Management Quality

    access_time02-04-2026 remove_red_eye827 personTiyo Surya Sakti
  2. Kampung Rambutan Terminal Sees Increase in Intercity Bus Passengers

    access_time03-04-2026 remove_red_eye760 personNurito
  3. Banners Prohibiting Illegal Parking Levies Installed at Blok M Square

    access_time02-04-2026 remove_red_eye667 personTiyo Surya Sakti
  4. West Jakarta BPN Holds Mobile Land Service in Kembangan

    access_time06-04-2026 remove_red_eye544 personBudhi Firmansyah Surapati
  5. Jakarta to Host Lebaran Betawi Next Week at Lapangan Banteng

    access_time03-04-2026 remove_red_eye509 personFakhrizal Fakhri