You don't have javascript enabled. Good luck with that.
Pencarian
Desember, Normalisasi Kali Ciliwung Ditargetkan Rampung

Ciliwung River Normalization Targeted to Finish This December

The normalization project for Ciliwung River in Kampung Pulo, Kampung Melayu Urban Village has reached 36 percent.

The road is two ways. It is hoped to finish in December

The project includes dredging, widening, installing sheetpile, providing jogging track, and inspection road along 1,950 meter. It is targeted to finish in December this year.

Agus Triwibowo, project manager, said the first stage of this project is dredging the river and continued by widening the river between 35 up to 50 meter.

129 Illegal Buildings Around Tugu Tani will Be Demolished

"Next are installing sheetpile and cropingphile, also jogging track as wide as three meter," he said, Monday (10/12).

Furthermore, road inspection will be constructed along the river bank by 7.2 meter of width starting from Kampung Melayu bridge up to Tongtek. Later on, the road will be used as alternative access from Tebet towards Matraman Raya.

"The road is two ways. It is hoped to finish in December," he disclosed.

Linked News
Popular News indeks
  1. Transjakarta Adjusts Operations Due to Public Demonstration

    access_time12-06-2026 remove_red_eye1417 personAldi Geri Lumban Tobing
  2. Pramono Launches Jumbo Biopores, Aims for Jakarta Waste Management Blueprint

    access_time07-06-2026 remove_red_eye1009 personDessy Suciati
  3. Pramono: Transjabodetabek Fare Adjustment Based on Careful Consideration

    access_time10-06-2026 remove_red_eye988 personDessy Suciati
  4. BTN JAKIM 2026, Traffic Engineering and Alternative Routes Provided

    access_time11-06-2026 remove_red_eye783 personAldi Geri Lumban Tobing
  5. Accelerating Jakarta`s Global City Development, Pramono Inaugurates Urban Knowledge Hub

    access_time08-06-2026 remove_red_eye681 personDessy Suciati