You don't have javascript enabled. Good luck with that.
Pencarian
Desember, Normalisasi Kali Ciliwung Ditargetkan Rampung

Ciliwung River Normalization Targeted to Finish This December

The normalization project for Ciliwung River in Kampung Pulo, Kampung Melayu Urban Village has reached 36 percent.

The road is two ways. It is hoped to finish in December

The project includes dredging, widening, installing sheetpile, providing jogging track, and inspection road along 1,950 meter. It is targeted to finish in December this year.

Agus Triwibowo, project manager, said the first stage of this project is dredging the river and continued by widening the river between 35 up to 50 meter.

129 Illegal Buildings Around Tugu Tani will Be Demolished

"Next are installing sheetpile and cropingphile, also jogging track as wide as three meter," he said, Monday (10/12).

Furthermore, road inspection will be constructed along the river bank by 7.2 meter of width starting from Kampung Melayu bridge up to Tongtek. Later on, the road will be used as alternative access from Tebet towards Matraman Raya.

"The road is two ways. It is hoped to finish in December," he disclosed.

Linked News
Popular News indeks
  1. Transjakarta Modifies Mikrotrans Routes JAK 48A, JAK 50, and JAK 79

    access_time12-10-2026 remove_red_eye542 personAldi Geri Lumban Tobing
  2. Dengue Cases Decline in Jakarta as Prevention Efforts Intensify

    access_time16-10-2026 remove_red_eye469 personAldi Geri Lumban Tobing
  3. CiLung Festival Lets Visitors Ride Boats Made from Recycled Plastic Bottles

    access_time16-10-2026 remove_red_eye459 personAldi Geri Lumban Tobing
  4. An-Nur Floating Mosque Opens After Years of Waiting

    access_time16-10-2026 remove_red_eye413 personFakhrizal Fakhri
  5. Rano Requests Education Agency Hold Disaster Mitigation Training

    access_time16-10-2026 remove_red_eye394 personBudhi Firmansyah Surapati