Desember, Normalisasi Kali Ciliwung Ditargetkan Rampung

Ciliwung River Normalization Targeted to Finish This December

The normalization project for Ciliwung River in Kampung Pulo, Kampung Melayu Urban Village has reached 36 percent.

The road is two ways. It is hoped to finish in December

The project includes dredging, widening, installing sheetpile, providing jogging track, and inspection road along 1,950 meter. It is targeted to finish in December this year.

Agus Triwibowo, project manager, said the first stage of this project is dredging the river and continued by widening the river between 35 up to 50 meter.

129 Illegal Buildings Around Tugu Tani will Be Demolished

"Next are installing sheetpile and cropingphile, also jogging track as wide as three meter," he said, Monday (10/12).

Furthermore, road inspection will be constructed along the river bank by 7.2 meter of width starting from Kampung Melayu bridge up to Tongtek. Later on, the road will be used as alternative access from Tebet towards Matraman Raya.

"The road is two ways. It is hoped to finish in December," he disclosed.

Linked News
Popular News indeks
  1. Open for All: Jakarta City Hall Welcomes Visitors for Namu Balai Kota

    access_time03-10-2026 remove_red_eye533 personDessy Suciati
  2. Jakarta Builds Five New Animal Health Centers to Expand Veterinary Services

    access_time30-09-2026 remove_red_eye496 personAldi Geri Lumban Tobing
  3. Transjakarta Reaffirms Ban on Busking in Mikrotrans and Bus Stops

    access_time02-10-2026 remove_red_eye453 personAldi Geri Lumban Tobing
  4. Commission D Supports Reserve Fund for Long-Term Infrastructure

    access_time02-10-2026 remove_red_eye424 personFakhrizal Fakhri
  5. Buildings on the Sidewalk in Front of Plumpang Transjakarta Bus Stop Demolished

    access_time30-09-2026 remove_red_eye412 personAnita Karyati