You don't have javascript enabled. Good luck with that.
Pencarian
Desember, Normalisasi Kali Ciliwung Ditargetkan Rampung

Ciliwung River Normalization Targeted to Finish This December

The normalization project for Ciliwung River in Kampung Pulo, Kampung Melayu Urban Village has reached 36 percent.

The road is two ways. It is hoped to finish in December

The project includes dredging, widening, installing sheetpile, providing jogging track, and inspection road along 1,950 meter. It is targeted to finish in December this year.

Agus Triwibowo, project manager, said the first stage of this project is dredging the river and continued by widening the river between 35 up to 50 meter.

129 Illegal Buildings Around Tugu Tani will Be Demolished

"Next are installing sheetpile and cropingphile, also jogging track as wide as three meter," he said, Monday (10/12).

Furthermore, road inspection will be constructed along the river bank by 7.2 meter of width starting from Kampung Melayu bridge up to Tongtek. Later on, the road will be used as alternative access from Tebet towards Matraman Raya.

"The road is two ways. It is hoped to finish in December," he disclosed.

Linked News
Popular News indeks
  1. China-Based Training Equips PR Professionals and Journalists for Digital Media Transformation

    access_time19-07-2026 remove_red_eye1559 personFakhrizal Fakhri
  2. Jakarta Supports Social Media Restrictions for Children

    access_time20-07-2026 remove_red_eye1171 personFakhrizal Fakhri
  3. Commission E Enlists Religious Leaders to Fight Drugs and Violence

    access_time24-07-2026 remove_red_eye1158 personFakhrizal Fakhri
  4. Fire at Spark Sport Academy Pondok Bambu Successfully Extinguished

    access_time20-07-2026 remove_red_eye1002 personNurito
  5. Pramono and Coop Minister Kick Off Gen Coop Run 5K

    access_time19-07-2026 remove_red_eye800 personFakhrizal Fakhri