You don't have javascript enabled. Good luck with that.
Pencarian
Desember, Normalisasi Kali Ciliwung Ditargetkan Rampung

Ciliwung River Normalization Targeted to Finish This December

The normalization project for Ciliwung River in Kampung Pulo, Kampung Melayu Urban Village has reached 36 percent.

The road is two ways. It is hoped to finish in December

The project includes dredging, widening, installing sheetpile, providing jogging track, and inspection road along 1,950 meter. It is targeted to finish in December this year.

Agus Triwibowo, project manager, said the first stage of this project is dredging the river and continued by widening the river between 35 up to 50 meter.

129 Illegal Buildings Around Tugu Tani will Be Demolished

"Next are installing sheetpile and cropingphile, also jogging track as wide as three meter," he said, Monday (10/12).

Furthermore, road inspection will be constructed along the river bank by 7.2 meter of width starting from Kampung Melayu bridge up to Tongtek. Later on, the road will be used as alternative access from Tebet towards Matraman Raya.

"The road is two ways. It is hoped to finish in December," he disclosed.

Linked News
Popular News indeks
  1. Jakarta Council Begins Deliberations on New Population and Housing Bylaws

    access_time21-08-2026 remove_red_eye1739 personFakhrizal Fakhri
  2. Jakarta Assesses Needs and Coordinates Aid for NTT Earthquake Victims

    access_time16-08-2026 remove_red_eye734 personAldi Geri Lumban Tobing
  3. Pramono: Independence must Be Manifested Through Concrete Action

    access_time17-08-2026 remove_red_eye684 personDessy Suciati
  4. Jakarta Prepares Aid for NTT Earthquake Victims

    access_time16-08-2026 remove_red_eye683 personDessy Suciati
  5. Pramono Commends Madurese Community for Their Vital Role in Building Jakarta

    access_time19-08-2026 remove_red_eye655 personDessy Suciati