You don't have javascript enabled. Good luck with that.
Pencarian
Desember, Normalisasi Kali Ciliwung Ditargetkan Rampung
.
photo Budhi Firmansyah Surapati - Beritajakarta.id

Ciliwung River Normalization Targeted to Finish This December

The normalization project for Ciliwung River in Kampung Pulo, Kampung Melayu Urban Village has reached 36 percent.

The road is two ways. It is hoped to finish in December

The project includes dredging, widening, installing sheetpile, providing jogging track, and inspection road along 1,950 meter. It is targeted to finish in December this year.

Agus Triwibowo, project manager, said the first stage of this project is dredging the river and continued by widening the river between 35 up to 50 meter.

129 Illegal Buildings Around Tugu Tani will Be Demolished

"Next are installing sheetpile and cropingphile, also jogging track as wide as three meter," he said, Monday (10/12).

Furthermore, road inspection will be constructed along the river bank by 7.2 meter of width starting from Kampung Melayu bridge up to Tongtek. Later on, the road will be used as alternative access from Tebet towards Matraman Raya.

"The road is two ways. It is hoped to finish in December," he disclosed.

Linked News
Popular News indeks
  1. Most Residents Satisfied with Pramono-Rano's Performance

    access_time25-06-2025 remove_red_eye312 personDessy Suciati
  2. Pramono Ensures KJP will Continue to Be Distributed

    access_time26-06-2025 remove_red_eye307 personDessy Suciati
  3. No Car Free Day on June 29 to Support Jakarta International Marathon 2025

    access_time24-06-2025 remove_red_eye277 personAldi Geri Lumban Tobing
  4. Here are Parking Spaces around Lapangan Banteng for Jakarta's Anniversary

    access_time21-06-2025 remove_red_eye270 personAldi Geri Lumban Tobing
  5. Governor Pramono: Jakarta E-Prix 2025 in Ancol is Amazing!

    access_time21-06-2025 remove_red_eye270 personDessy Suciati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik