You don't have javascript enabled. Good luck with that.
Pencarian
Desember, Normalisasi Kali Ciliwung Ditargetkan Rampung

Ciliwung River Normalization Targeted to Finish This December

The normalization project for Ciliwung River in Kampung Pulo, Kampung Melayu Urban Village has reached 36 percent.

The road is two ways. It is hoped to finish in December

The project includes dredging, widening, installing sheetpile, providing jogging track, and inspection road along 1,950 meter. It is targeted to finish in December this year.

Agus Triwibowo, project manager, said the first stage of this project is dredging the river and continued by widening the river between 35 up to 50 meter.

129 Illegal Buildings Around Tugu Tani will Be Demolished

"Next are installing sheetpile and cropingphile, also jogging track as wide as three meter," he said, Monday (10/12).

Furthermore, road inspection will be constructed along the river bank by 7.2 meter of width starting from Kampung Melayu bridge up to Tongtek. Later on, the road will be used as alternative access from Tebet towards Matraman Raya.

"The road is two ways. It is hoped to finish in December," he disclosed.

Linked News
Popular News indeks
  1. BI and Jakarta Government Deepen Investment, Creative Economy Collaboration

    access_time09-11-2026 remove_red_eye534 personAldi Geri Lumban Tobing
  2. Governor Approves Removal of Seven Unauthorized Houses on Dispora Land

    access_time13-11-2026 remove_red_eye502 personFakhrizal Fakhri
  3. Pramono Outlines Measures to Address Five Issues in Kramat Jati

    access_time13-11-2026 remove_red_eye495 personFakhrizal Fakhri
  4. Transjakarta Offers Free Rides for Jakarta Vertical Run 2026 Participants

    access_time14-11-2026 remove_red_eye494 personAldi Geri Lumban Tobing
  5. Jakarta Esports 2026 Draws Enthusiastic Crowds at M Bloc Space

    access_time13-11-2026 remove_red_eye481 personTiyo Surya Sakti