Akhir Desember Fly Over Permata Hijau Rampung

Permata Hijau Flyover Construction to Finish This December

Jakarta Bina Marga Department predicted Permata Hijau, Kebayoran Lama Flyover construction will be complete by the end of year. The current construction has reached 87 percent and cost Rp 131 billion.

The contruction progress has reached 87 percent from the initial plan 71.12 percent by deviation occurs 15.37 percent

 

“The construction progress has reached 87 percent from the initial plan 71.12 percent by deviation occurs 15.37 percent,” said Hananto, Section Head of overpass and intersection division for Jakarta Bina Marga Department, Thursday (10/22).

Illegal Parking Under Roxy Flyover Rampant

 

According to him, the construction of 623 meters long flyover now is remaining box girder project above railway and finishing touch.

 

The flyover width is about 10 meters and there will be two lanes by each width is 7.8 meters. The remaining area will be used for pedestrian track.

 

“There will be two lanes towards Permata Hijau and Patal Senayan,” he disclosed.

Linked News
Popular News indeks
  1. Jakarta Removes Gibran’s Portraits Across All Government Offices

    access_time16-11-2026 remove_red_eye1248 personFakhrizal Fakhri
  2. Welcoming BTS's Concert in December 2026, Jakarta is Dressed in Purple

    access_time16-11-2026 remove_red_eye551 personFakhrizal Fakhri
  3. Pramono Pushes to Complete Long-Delayed Pluit JLNT by March 2027

    access_time20-11-2026 remove_red_eye539 personDessy Suciati
  4. Jakarta Strengthens ASEAN Cooperation on Climate, Transport, and Youth

    access_time20-11-2026 remove_red_eye528 personFolmer
  5. Jakarta Hosts 2026 UCWDC Asian Championship with 280 Dancers from Five Countries

    access_time20-11-2026 remove_red_eye513 personBudhi Firmansyah Surapati