Akhir Desember Fly Over Permata Hijau Rampung
.
photo Izzudin - Beritajakarta.id

Permata Hijau Flyover Construction to Finish This December

Jakarta Bina Marga Department predicted Permata Hijau, Kebayoran Lama Flyover construction will be complete by the end of year. The current construction has reached 87 percent and cost Rp 131 billion.

The contruction progress has reached 87 percent from the initial plan 71.12 percent by deviation occurs 15.37 percent

 

“The construction progress has reached 87 percent from the initial plan 71.12 percent by deviation occurs 15.37 percent,” said Hananto, Section Head of overpass and intersection division for Jakarta Bina Marga Department, Thursday (10/22).

Illegal Parking Under Roxy Flyover Rampant

 

According to him, the construction of 623 meters long flyover now is remaining box girder project above railway and finishing touch.

 

The flyover width is about 10 meters and there will be two lanes by each width is 7.8 meters. The remaining area will be used for pedestrian track.

 

“There will be two lanes towards Permata Hijau and Patal Senayan,” he disclosed.

Linked News
Popular News indeks
  1. 21 Damaged Roads in Cilincing Repaired

    access_time11-07-2025 remove_red_eye550 personAnita Karyati
  2. Implementation of Free Schools Awaits Central Regulations, Pramono Says

    access_time11-07-2025 remove_red_eye460 personDessy Suciati
  3. Transjakarta Targets Planting 100,000 Mangroves

    access_time12-07-2025 remove_red_eye392 personBudhi Firmansyah Surapati
  4. Rano Karno Celebrates City's Anniversary with Kamal Residents

    access_time12-07-2025 remove_red_eye387 personFolmer
  5. Commission E Pushes for Accelerated Health Center Revitalization

    access_time11-07-2025 remove_red_eye369 personFakhrizal Fakhri

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik