Akhir Desember Fly Over Permata Hijau Rampung
.
photo Izzudin - Beritajakarta.id

Permata Hijau Flyover Construction to Finish This December

Jakarta Bina Marga Department predicted Permata Hijau, Kebayoran Lama Flyover construction will be complete by the end of year. The current construction has reached 87 percent and cost Rp 131 billion.

The contruction progress has reached 87 percent from the initial plan 71.12 percent by deviation occurs 15.37 percent

 

“The construction progress has reached 87 percent from the initial plan 71.12 percent by deviation occurs 15.37 percent,” said Hananto, Section Head of overpass and intersection division for Jakarta Bina Marga Department, Thursday (10/22).

Illegal Parking Under Roxy Flyover Rampant

 

According to him, the construction of 623 meters long flyover now is remaining box girder project above railway and finishing touch.

 

The flyover width is about 10 meters and there will be two lanes by each width is 7.8 meters. The remaining area will be used for pedestrian track.

 

“There will be two lanes towards Permata Hijau and Patal Senayan,” he disclosed.

Linked News
Popular News indeks
  1. Pramono Prioritizes Construction of Cakung Regional Hospital

    access_time18-04-2025 remove_red_eye425 personFakhrizal Fakhri
  2. 60 Joint Personnel Conduct Community Work in Karet Tengsin

    access_time13-04-2025 remove_red_eye407 personBudhi Firmansyah Surapati
  3. Governor Pramono Joins Cycling in Jakarta Silaturahride 2025

    access_time19-04-2025 remove_red_eye310 personBudhi Firmansyah Surapati
  4. Free Transportation Services to Facilitate Residents' Mobility

    access_time17-04-2025 remove_red_eye296 personDessy Suciati
  5. Jakarta to be Designed as a Film City

    access_time13-04-2025 remove_red_eye285 personFakhrizal Fakhri

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik