Akhir Desember Fly Over Permata Hijau Rampung
.
photo Izzudin - Beritajakarta.id

Permata Hijau Flyover Construction to Finish This December

Jakarta Bina Marga Department predicted Permata Hijau, Kebayoran Lama Flyover construction will be complete by the end of year. The current construction has reached 87 percent and cost Rp 131 billion.

The contruction progress has reached 87 percent from the initial plan 71.12 percent by deviation occurs 15.37 percent

 

“The construction progress has reached 87 percent from the initial plan 71.12 percent by deviation occurs 15.37 percent,” said Hananto, Section Head of overpass and intersection division for Jakarta Bina Marga Department, Thursday (10/22).

Illegal Parking Under Roxy Flyover Rampant

 

According to him, the construction of 623 meters long flyover now is remaining box girder project above railway and finishing touch.

 

The flyover width is about 10 meters and there will be two lanes by each width is 7.8 meters. The remaining area will be used for pedestrian track.

 

“There will be two lanes towards Permata Hijau and Patal Senayan,” he disclosed.

Linked News
Popular News indeks
  1. Water Channel Dredging on Bendungan Melayu Reaches 50 Percent

    access_time18-09-2024 remove_red_eye828 personAnita Karyati
  2. Jakarta Leads Medal Standing at PON XXI

    access_time17-09-2024 remove_red_eye781 personFolmer
  3. Jakarta Aeromodelling Team Grabs First Gold Medal

    access_time16-09-2024 remove_red_eye556 personAldi Geri Lumban Tobing
  4. Area Arrangement on Jalan Kramat to Complete this Weekend

    access_time17-09-2024 remove_red_eye428 personTiyo Surya Sakti
  5. Area Arrangement on Jalan Setapak Reaches 95 Percent

    access_time14-09-2024 remove_red_eye363 personTiyo Surya Sakti