Akhir Desember Fly Over Permata Hijau Rampung

Permata Hijau Flyover Construction to Finish This December

Jakarta Bina Marga Department predicted Permata Hijau, Kebayoran Lama Flyover construction will be complete by the end of year. The current construction has reached 87 percent and cost Rp 131 billion.

The contruction progress has reached 87 percent from the initial plan 71.12 percent by deviation occurs 15.37 percent

 

“The construction progress has reached 87 percent from the initial plan 71.12 percent by deviation occurs 15.37 percent,” said Hananto, Section Head of overpass and intersection division for Jakarta Bina Marga Department, Thursday (10/22).

Illegal Parking Under Roxy Flyover Rampant

 

According to him, the construction of 623 meters long flyover now is remaining box girder project above railway and finishing touch.

 

The flyover width is about 10 meters and there will be two lanes by each width is 7.8 meters. The remaining area will be used for pedestrian track.

 

“There will be two lanes towards Permata Hijau and Patal Senayan,” he disclosed.

Linked News
Popular News indeks
  1. Central Jakarta Administration Acts Swiftly to Handle Kebon Kosong Fire

    access_time02-06-2026 remove_red_eye1417 personFolmer
  2. Jakarta Waives Motor Vehicle Tax Fines and Title Transfer Fees

    access_time01-06-2026 remove_red_eye854 personAldi Geri Lumban Tobing
  3. Commemorating Vesak, Jakarta Lights Up with Illumination of Jakarta 2026

    access_time30-05-2026 remove_red_eye653 personBudhi Firmansyah Surapati
  4. Seniors Participate in Pasti Bisa Berkarya at MRT Stations

    access_time02-06-2026 remove_red_eye602 personAldi Geri Lumban Tobing
  5. Krendang Fire Victims Receive Proper Support and Assistance

    access_time29-05-2026 remove_red_eye475 personBudhi Firmansyah Surapati