Akhir Desember Fly Over Permata Hijau Rampung
.
photo Izzudin - Beritajakarta.id

Permata Hijau Flyover Construction to Finish This December

Jakarta Bina Marga Department predicted Permata Hijau, Kebayoran Lama Flyover construction will be complete by the end of year. The current construction has reached 87 percent and cost Rp 131 billion.

The contruction progress has reached 87 percent from the initial plan 71.12 percent by deviation occurs 15.37 percent

 

“The construction progress has reached 87 percent from the initial plan 71.12 percent by deviation occurs 15.37 percent,” said Hananto, Section Head of overpass and intersection division for Jakarta Bina Marga Department, Thursday (10/22).

Illegal Parking Under Roxy Flyover Rampant

 

According to him, the construction of 623 meters long flyover now is remaining box girder project above railway and finishing touch.

 

The flyover width is about 10 meters and there will be two lanes by each width is 7.8 meters. The remaining area will be used for pedestrian track.

 

“There will be two lanes towards Permata Hijau and Patal Senayan,” he disclosed.

Linked News
Popular News indeks
  1. Takjil Supervision in Central Jakarta Begins Second Week

    access_time02-03-2025 remove_red_eye475 personBudhi Firmansyah Surapati
  2. Dishub: Lay Bay Remains Optimal to Support Public Transportation User Comfort

    access_time02-03-2025 remove_red_eye409 personAldi Geri Lumban Tobing
  3. Traffic Diverted on Jalan Jatinegara Barat as Floods Hit Jakarta

    access_time04-03-2025 remove_red_eye379 personNurito
  4. Job Fair at Pluit Junction Mall Offers 1,500 Vacancies

    access_time05-03-2025 remove_red_eye275 personAnita Karyati
  5. Rano Supports Schools to Organize Study Tours to Museums

    access_time08-03-2025 remove_red_eye272 personBudhi Firmansyah Surapati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik