photo Izzudin - Beritajakarta.id

Permata Hijau Flyover Construction to Finish This December

Jakarta Bina Marga Department predicted Permata Hijau, Kebayoran Lama Flyover construction will be complete by the end of year. The current construction has reached 87 percent and cost Rp 131 billion.

The contruction progress has reached 87 percent from the initial plan 71.12 percent by deviation occurs 15.37 percent

 

“The construction progress has reached 87 percent from the initial plan 71.12 percent by deviation occurs 15.37 percent,” said Hananto, Section Head of overpass and intersection division for Jakarta Bina Marga Department, Thursday (10/22).

Illegal Parking Under Roxy Flyover Rampant

 

According to him, the construction of 623 meters long flyover now is remaining box girder project above railway and finishing touch.

 

The flyover width is about 10 meters and there will be two lanes by each width is 7.8 meters. The remaining area will be used for pedestrian track.

 

“There will be two lanes towards Permata Hijau and Patal Senayan,” he disclosed.

Linked News
Popular News indeks
  1. Cloudy Morning, Rainy Afternoon this Tuesday, BMKG Says

    access_time17-06-2025 remove_red_eye307 personDessy Suciati
  2. Jakarta Fair Kemayoran Begins, Hailing City’s 498th Anniversary

    access_time20-06-2025 remove_red_eye301 personDessy Suciati
  3. Governor Pramono: Jakarta E-Prix 2025 in Ancol is Amazing!

    access_time21-06-2025 remove_red_eye247 personDessy Suciati
  4. Here are Parking Spaces around Lapangan Banteng for Jakarta's Anniversary

    access_time21-06-2025 remove_red_eye232 personAldi Geri Lumban Tobing
  5. Jakarta's Anniversary, Motor Vehicle Tax Sanctions in Jakarta Removed

    access_time18-06-2025 remove_red_eye212 personDessy Suciati

Hitung Mundur 22 Juni 2027

728
Hari
03
Jam
06
Menit
49
Detik