Akhir Desember Fly Over Permata Hijau Rampung
.
photo Izzudin - Beritajakarta.id

Permata Hijau Flyover Construction to Finish This December

Jakarta Bina Marga Department predicted Permata Hijau, Kebayoran Lama Flyover construction will be complete by the end of year. The current construction has reached 87 percent and cost Rp 131 billion.

The contruction progress has reached 87 percent from the initial plan 71.12 percent by deviation occurs 15.37 percent

 

“The construction progress has reached 87 percent from the initial plan 71.12 percent by deviation occurs 15.37 percent,” said Hananto, Section Head of overpass and intersection division for Jakarta Bina Marga Department, Thursday (10/22).

Illegal Parking Under Roxy Flyover Rampant

 

According to him, the construction of 623 meters long flyover now is remaining box girder project above railway and finishing touch.

 

The flyover width is about 10 meters and there will be two lanes by each width is 7.8 meters. The remaining area will be used for pedestrian track.

 

“There will be two lanes towards Permata Hijau and Patal Senayan,” he disclosed.

Linked News
Popular News indeks
  1. Commission D Legislator Supports Park Monitoring Optimization

    access_time20-01-2025 remove_red_eye1535 personDessy Suciati
  2. Realizing Food Self-Sufficiency, Jakarta Holds Simultaneous Planting Activity

    access_time21-01-2025 remove_red_eye956 personAldi Geri Lumban Tobing
  3. Gulkarmat to Intensify Fire Mitigation Education

    access_time22-01-2025 remove_red_eye492 personBudhi Firmansyah Surapati
  4. BMKG Warns of Potential High Rainfall in Jakarta

    access_time22-01-2025 remove_red_eye451 personDessy Suciati
  5. City and Kejati Forge Cooperation for Good Government Governance

    access_time21-01-2025 remove_red_eye426 personFolmer