Akhir Desember Fly Over Permata Hijau Rampung

Permata Hijau Flyover Construction to Finish This December

Jakarta Bina Marga Department predicted Permata Hijau, Kebayoran Lama Flyover construction will be complete by the end of year. The current construction has reached 87 percent and cost Rp 131 billion.

The contruction progress has reached 87 percent from the initial plan 71.12 percent by deviation occurs 15.37 percent

 

“The construction progress has reached 87 percent from the initial plan 71.12 percent by deviation occurs 15.37 percent,” said Hananto, Section Head of overpass and intersection division for Jakarta Bina Marga Department, Thursday (10/22).

Illegal Parking Under Roxy Flyover Rampant

 

According to him, the construction of 623 meters long flyover now is remaining box girder project above railway and finishing touch.

 

The flyover width is about 10 meters and there will be two lanes by each width is 7.8 meters. The remaining area will be used for pedestrian track.

 

“There will be two lanes towards Permata Hijau and Patal Senayan,” he disclosed.

Linked News
Popular News indeks
  1. City Council Strengthens Synergy with Central Legislators to Support Jakarta`s Development

    access_time30-07-2026 remove_red_eye1076 personFakhrizal Fakhri
  2. Jakarta Partners with Five Satellite Cities for Greater Jakarta Connected Initiative

    access_time30-07-2026 remove_red_eye603 personBudhi Firmansyah Surapati
  3. Still Rp 3,500! No Fare Change for Transjakarta’s Kalideres–Soetta Route

    access_time01-08-2026 remove_red_eye502 personAldi Geri Lumban Tobing
  4. Jakarta Reaffirms Commitment to Preserving Cultural Heritage

    access_time31-07-2026 remove_red_eye492 personDessy Suciati
  5. Pramono Praises Young Innovators at the Jakarta Robotic Games 2026

    access_time28-07-2026 remove_red_eye491 personDessy Suciati