Permata Hijau Flyover Construction to Finish This December
access_time October 23 2015 11:09 AM remove_red_eye 1547
Reported by Izzudin | Translated by Trias Risangayu
Reported by Izzudin | Translated by Trias Risangayu
Jakarta Bina Marga Department predicted Permata Hijau, Kebayoran Lama Flyover construction will be complete by the end of year. The current construction has reached 87 percent and cost Rp 131 billion.
The contruction progress has reached 87 percent from the initial plan 71.12 percent by deviation occurs 15.37 percent
“The construction progress has reached 87 percent from the initial plan 71.12 percent by deviation occurs 15.37 percent,” said Hananto, Section Head of over
pass and intersection division for Jakarta Bina Marga Department, Thursday (10/22).Illegal Parking Under Roxy Flyover Rampant
According to him, the construction of 623 meters long flyover now is remaining box girder project above railway and finishing touch.
The flyover width is about 10 meters and there will be two lanes by each width is 7.8 meters. The remaining area will be used for pedestrian track.
“There will be two lanes towards Permata Hijau and Patal Senayan,” he disclosed.