Akhir Desember Fly Over Permata Hijau Rampung

Permata Hijau Flyover Construction to Finish This December

Jakarta Bina Marga Department predicted Permata Hijau, Kebayoran Lama Flyover construction will be complete by the end of year. The current construction has reached 87 percent and cost Rp 131 billion.

The contruction progress has reached 87 percent from the initial plan 71.12 percent by deviation occurs 15.37 percent

 

“The construction progress has reached 87 percent from the initial plan 71.12 percent by deviation occurs 15.37 percent,” said Hananto, Section Head of overpass and intersection division for Jakarta Bina Marga Department, Thursday (10/22).

Illegal Parking Under Roxy Flyover Rampant

 

According to him, the construction of 623 meters long flyover now is remaining box girder project above railway and finishing touch.

 

The flyover width is about 10 meters and there will be two lanes by each width is 7.8 meters. The remaining area will be used for pedestrian track.

 

“There will be two lanes towards Permata Hijau and Patal Senayan,” he disclosed.

Linked News
Popular News indeks
  1. Water Channel on Jalan SPG 7 Being Improved

    access_time18-09-2026 remove_red_eye802 personNurito
  2. Jakarta Govt Fully Backs Kanye West's Ye Live in Jakarta 2026

    access_time16-09-2026 remove_red_eye548 personDessy Suciati
  3. Jakarta Pushes to Strengthen Food Ecosystem

    access_time18-09-2026 remove_red_eye530 personAldi Geri Lumban Tobing
  4. Operations of the MV Doulos Hope Ship Library Delayed

    access_time18-09-2026 remove_red_eye437 personAnita Karyati
  5. Pramono Departs for New York to Discuss Climate and Food Crises

    access_time18-09-2026 remove_red_eye432 personDessy Suciati